Concordance: concepts compared

210 concepts · 9 frameworks

Which terms mean the same thing in ISO 21506, the PMBOK Guide, PRINCE2, Scrum and other frameworks? The concordance sets out all concepts side by side.

How to read the table

  • equivalent
  • closely related
  • partially overlapping
  • false friend
  • no underline: no entry of its own yet
  • no counterpart
  • not yet reviewed

Fundamentals

Basic project management terms that apply across all topics: what a project is, how it unfolds, what it depends on and when it is successful.

Fundamentals: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Change resulting from outputsnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Defined stage of a projectnamed by 3 of 9 frameworksNot yet reviewed: IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Direct result of an initiativenamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Influences and conditions around a projectnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Leading and controlling projectsnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Path of a product from idea to retirementnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Sequence of phases from project start to finishnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Unique, time-limited endeavour with its own objectivenamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation

Approaches and agility

Terms for traditional, agile and hybrid approaches and for typical agile working tools such as iterations, user stories and burn-down charts.

Approaches and agility: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Adapting the method to the undertakingnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, IPMA, Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Adaptive approach in short cyclesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Chart of remaining work over timenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Combination of plan-driven and agile approachesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Defined framework for how a project proceedsnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Leannot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
High-level timeline of key resultsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Item in an ordered work listnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Large requirement still to be broken downnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Plan-driven approachnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Relative size unit for agile work itemsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Requirement from the perspective of a user groupnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Simplest product version for learningnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Starting work only on demand or when capacity is freenamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, PRINCE2, IPMA, PM², Scrum, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Time-boxed work cyclenamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartnot yet reviewednot yet reviewed
User-centred development of solutionsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Working in fixed time framesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed

Project organization

Terms for roles, bodies and organizational forms in projects: who commissions, who leads, who decides and how projects are embedded in organizations.

Project organization: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Assigning responsibilities to tasksnamed by 3 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, Lean, Six Sigmanot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Chart of positions and relationships in an organizationnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Commissioning side of a projectnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, PRINCE2, IPMA, Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Delivering side of a projectnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, PRINCE2, IPMA, Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Direction and decision framework of a projectnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Framework for direction, decisions and oversightnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Hierarchical breakdown of the project organizationnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Independent assurance of a project for its directing levelnamed by 2 of 9 frameworksNot yet reviewed: PMI / PMBOK, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Leading role of the delivering sidenamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, IPMA, Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Organization structure with dual reportingnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Organization structure with single line of authoritynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Organization working mainly in projectsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Person responsible for managing a projectnamed by 4 of 9 frameworksNot yet reviewed: IPMA, Lean, Six Sigmanot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Project management support functionnamed by 4 of 9 frameworksNot yet reviewed: IPMA, Lean, Six Sigmanot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Representation of user interests in a projectnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, IPMA, Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Roles, bodies and authority in a projectnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Senior sponsoring role in a projectnamed by 5 of 9 frameworksNot yet reviewed: IPMA, Leannot yet reviewedno counterpartno counterpartnot yet reviewedno designation
Steering body of a projectnamed by 3 of 9 frameworksNot yet reviewed: ISO 21506, IPMA, Lean, Six Sigmanot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Team carrying out the project worknamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, PRINCE2, IPMA, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed

Portfolios and programmes

Terms for steering multiple initiatives: programmes, portfolios and multi-project management, and the benefits that go beyond the single project.

Portfolios and programmes: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Coordinated management of a programmenamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Group of related projects with a shared objectivenamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Person responsible for managing a portfolionamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Person responsible for managing a programmenamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Plan for managing a portfolionamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Plan for managing a programmenamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Planning and securing benefits of initiativesnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Positive effect of an initiative for stakeholdersnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Selecting and steering an organization's initiativesnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Set of initiatives managed togethernamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Translating strategy into objectives and actions across organizational levelsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, PRINCE2, IPMA, PM², Scrum, Kanban, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed

Initiating

Terms around the start of a project: from the first project proposal and the business case to formal authorization and the appointment of the project manager.

Initiating: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Assessment of whether an initiative is feasiblenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Economic justification of an initiativenamed by 3 of 9 frameworksNot yet reviewed: IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Formal authorization of a projectnamed by 5 of 9 frameworksNot yet reviewed: IPMA, Leannot yet reviewedno counterpartno counterpartnot yet reviewed
  • Project outlinepartially overlappingno entry yet
Launch meeting of a projectnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Opening stage of a projectnamed by 3 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, IPMA, Leannot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewed

Scope and requirements

Terms for what a project is to deliver: requirements, deliverables, statement of work, acceptance criteria and protection against scope creep.

Scope and requirements: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Condition a result must meetnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Leannot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Criteria for a finished resultnamed by 3 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Description of work to be performednamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Gradual uncontrolled expansion of scopenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Totality of results and work to be deliverednamed by 3 of 9 frameworksNot yet reviewed: IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Verifiable project resultnamed by 3 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation

Planning and project structure

Terms for planning and structuring a project: decomposition, breakdown structures, assumptions, constraints, dependencies and the project management plan.

Planning and project structure: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Circumstance assumed true for planningnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Comprehensive project management plannamed by 4 of 9 frameworksNot yet reviewed: IPMA, Scrum, Kanban, Lean, Six Sigma
  • Project management planPreferred termno entry yet
  • Project planequivalent
not yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Description of work breakdown structure elementsnamed by 3 of 9 frameworksNot yet reviewed: IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Fixed limitation on the options availablenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Hierarchical decomposition of project scopenamed by 4 of 9 frameworksNot yet reviewed: IPMA, PM², Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Identifier of work breakdown structure elementsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Progressively refined planningnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Reliance on another elementnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Smallest planning unit of the project structurenamed by 3 of 9 frameworksNot yet reviewed: IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Stepwise division into smaller unitsnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Working out the path to the project resultnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed

Scheduling

Terms relating to the schedule: activities, durations, effort, milestones, calendars and the techniques that can be used to shorten a schedule.

Scheduling: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Bar chart representation of a schedulenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Defined piece of work with a start and finishnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Overview of key project eventsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Rollup of several activities in the schedulenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Shortening a schedule without reducing scopenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Shortening through additional resourcesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Shortening through parallel worknamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Significant event in the course of a projectnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Tabular list of all activitiesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Time span between start and finish of an activitynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Timing of project worknamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Working time rules of a projectnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed

Network planning

Terms of network planning: network diagram types, logical relationships, earliest and latest dates, float and the critical path as the basis for dates.

Network planning: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Activity on which another dependsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Activity that depends on anothernamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Activity without scheduling flexibilitynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Brought-forward start relative to the predecessornamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Calculation method for dates and floatnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Calculation of earliest datesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Calculation of latest datesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Diagram of activities and their dependenciesnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Earliest possible finish of an activitynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Earliest possible start of an activitynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Finish after another activity finishesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Finish after another activity startsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Latest allowable finish of an activitynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Latest allowable start of an activitynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Longest sequence of activities without floatnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Network diagram with activities on nodesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Schedule estimation with three values per activitynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Scheduling dependency between two activitiesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Scheduling flexibility relative to project completionnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Scheduling flexibility relative to successorsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Scheduling with aggregated buffersnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Start after another activity startsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Start after the predecessor finishesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Waiting time between predecessor and successornamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
  • LagPreferred term

Resources and estimating

Terms for resources and estimating: planning demand and capacity, levelling resources and estimating effort, duration or cost with suitable methods.

Resources and estimating: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Adjusting the schedule to available capacitynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Amount of labour a task requiresnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Determining resource needs and deploymentnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Estimating from comparable initiativesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Estimating from the bottom upnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Estimating using statistical parametersnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Estimating with several values per quantitynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Hierarchical breakdown of resourcesnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Judgement by expertsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed

Cost and economic viability

Terms for cost and economic viability: cost estimating and planning, budgets, cost types and metrics for the economic evaluation of initiatives.

Cost and economic viability: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Approved funds of a projectnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Setting costs by time and project componentnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Total costs over the service lifenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed

Risks and opportunities

Terms of risk management: identifying, assessing and responding to risks and opportunities, building reserves and quantifying overall uncertainty.

Risks and opportunities: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Acceptable level of risknamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Allowance for known risksnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Arrangements for risk management in a projectnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Central list of project risksnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Consciously accepting a risknamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Eliminating a risknamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Evaluating decisions under uncertainty as a treenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Examination of identified risksnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Grid of probability and impactnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Group of similar risksnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Hierarchical breakdown of risk sourcesnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Identifying potential risksnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Numerical assessment of overall risknamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Pre-planned response to an occurring risknamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Probability-weighted financial effectnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Rating risks by probability and impactnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Reducing probability or impactnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Reserve for unforeseen worknamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Risk arising from a responsenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Risk in a projectnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Risk remaining after responsesnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Risk with a negative effect on project objectivesnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Risk with a positive effect on project objectivesnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Selecting and implementing risk responsesnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Shifting the consequences of a risk to a third partynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Systematic handling of uncertainty in a projectnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Threshold at which a risk triggers actionnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Unplanned makeshift solution to an occurring problemnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed

Quality

Terms for quality in projects: quality management, inspection and verification, statistical process control, causes of defects and continual improvement.

Quality: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Correcting a defective resultnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Costs of prevention, appraisal and failurenamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Leannot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewed
Cycle of plan, do, check and actnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Evidence of fitness for purposenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Evidence that requirements are metnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Finding the underlying cause of a problemnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Independent review of a projectnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Planning, assuring and controlling qualitynamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Setting quality objectives and checksnamed by 3 of 9 frameworksNot yet reviewed: ISO 21506, IPMA, PM², Scrum, Kanban, Leannot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed

Stakeholders and communication

Terms for stakeholders and communication: identifying and engaging stakeholders, planning information and making project status traceable in reports.

Stakeholders and communication: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Arrangements for project communicationnamed by 3 of 9 frameworksNot yet reviewed: IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Engaging all involved and affected partiesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Identifying and assessing stakeholdersnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, PRINCE2, IPMA, Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Parties involved in or affected by an initiativenamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Regular project status reportnamed by 3 of 9 frameworksNot yet reviewed: PMI / PMBOK, IPMA, Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation

Leadership and teamwork

Terms for leadership and teamwork: team development, ground rules, conflicts and crises, project culture and dealing with change in the organization.

Leadership and teamwork: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Explicitly agreed working rulesnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Permanently equipped room for visibly steering an undertakingnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, PRINCE2, IPMA, PM², Scrum, Kanban, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Shared workplace of a project teamnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed

Contracts and procurement

Terms for contracts and procurement: contract types, tendering and bids, supplier selection, claims and the management of ongoing contracts.

Contracts and procurement: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Contract billed by effortnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Contract reimbursing actual costsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Contract with a pre-agreed pricenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed

Monitoring and control

Terms for monitoring and control: plan-versus-actual comparison, earned value, forecasts, changes and actions that keep a project on course.

Monitoring and control: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Action against a potential deviationnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Action against an occurred deviationnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Actual cost of work performednamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Approved reference version of a plannamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Body deciding on changesnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Budgeted value of planned worknamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Controlled handling of changesnamed by 2 of 9 frameworksNot yet reviewed: ISO 21506, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Cost efficiency of work performednamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Cumulative development over the project durationnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Decision point between project phasesnamed by 5 of 9 frameworksNot yet reviewed: IPMA, Leannot yet reviewedno counterpartno counterpartnot yet reviewedno designation
Difference between earned value and actual costnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Difference between earned value and planned valuenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewed
Difference between plan and actualnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Estimate of final dates and costsnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Evaluating development across several data datesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Examining plan-versus-actual differencesnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Expected budget variance at completionnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Expected cost of the remaining worknamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Expected total cost at completionnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Formal request to change what was agreednamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Management unit for scope, budget and schedulenamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Managing components and versions of a resultnamed by 3 of 9 frameworksNot yet reviewed: IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Monitoring and controlling a projectnamed by 3 of 9 frameworksNot yet reviewed: PMI / PMBOK, IPMA, Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Occurring problem that needs resolutionnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Performance measurement using earned valuenamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Permitted margin for deviationsnamed by 2 of 9 frameworksNot yet reviewed: PMI / PMBOK, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Reference date for recorded project statusnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Register of issuesnamed by 3 of 9 frameworksNot yet reviewed: IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Schedule efficiency of work performednamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewednot yet reviewedno designation
Share of work completednamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Software environment for project datanamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Time-phased baseline for performance measurementnamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Total budget of the planned worknamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Value of work performednamed by 2 of 9 frameworksNot yet reviewed: PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation

Closing

Terms for the end of a project: acceptance and handover of results, formal closure and the capturing of lessons learned for future initiatives.

Closing: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Captured lessons from projectsnamed by 5 of 9 frameworksNot yet reviewed: IPMA, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewedno designation
Closing stage of a projectnamed by 3 of 9 frameworksNot yet reviewed: ISO 21506, PMI / PMBOK, IPMA, Leannot yet reviewednot yet reviewednot yet reviewedno counterpartno counterpartnot yet reviewed

Working techniques

Working techniques that help across many project topics: creativity, analysis and facilitation techniques for workshops, decisions and prioritization.

Working techniques: concepts and their designations by framework
ConceptISO 21506PMI / PMBOKPRINCE2IPMAPM²ScrumKanbanLeanSix Sigmageneral
Graphically organising thoughts around a topicnamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed
Strengths, weaknesses, opportunities and threats at a glancenamed by 1 of 9 frameworksNot yet reviewed: ISO 21506, PRINCE2, IPMA, PM², Scrum, Kanban, Lean, Six Sigmanot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewednot yet reviewed

The assignment to concepts and topic areas is editorial and not part of the frameworks. The original source is always authoritative.