Project management plan

Definition

In PMI usage, the project management plan is the document that sets out how a project is to be carried out, monitored, controlled and closed. It brings together the subsidiary plans, for example on managing scope, schedule, cost, quality, resources, communications, risk, procurement and stakeholders, and contains the approved baselines for scope, schedule and cost. It also sets out the change procedure and the chosen life cycle. The plan is elaborated progressively and, once approved, is changed only through change control. Its extent and level of detail depend on the size and nature of the project.

Equivalents in other frameworks

Concept Comprehensive project management plan · six frameworks reviewed · two false friends

Equivalents of Project management plan in other frameworks
FrameworkTerm thereRelationNote
PRINCE2Project Planfalse friendno overlapDespite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level.
generalProject planfalse friendno overlapThe project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery.
ISO 21506Project management plan no entry yetequivalent—
ISO 21506Project planequivalent—
PRINCE2Project Initiation Documentationclosely relatedCollection of management products that also includes the business case; its approval authorizes the project.
PM²Project Handbookclosely relatedcontains the management approach and management plans; work breakdown, effort, cost and schedule are in the project work plan

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Project management plan

Distinction

The project management plan as defined in ISO 21506 denotes the same thing from a cross-framework perspective. In everyday language a project plan is often understood to be just the schedule; the project management plan is considerably broader. The project charter authorizes the project, while the project management plan sets out how it will be managed.

In practice

For the relocation of a data centre, the project manager draws up a project management plan. It refers to a schedule with three moving weekends, a budget with a reserve, a communications plan for business units and customers, and a plan for managing risks. It also specifies that changes above 50,000 euros are decided by the steering committee. When one weekend has to be postponed, the change is approved and the plan is updated.

Frequently asked questions

Does the project management plan have to be a single document?

No. In larger projects it often consists of a main document that refers to separate subsidiary plans and baselines. What matters is that all parts are consistent and are approved and maintained together.

How is the plan handled in adaptive projects?

It is usually leaner and describes the framework, roles and cadence rather than detailed content. The actual work is then defined continuously in backlogs and iteration plans.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Project management plan. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-management-plan/

Short form

Project management plan (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/project-management-plan/ (retrieved 24 November 2026)

BibTeX
@misc{projectmanagementplan,
  title   = {Project management plan},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/project-management-plan/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/project-management-plan/">
  <p>Central planning document of a project that bundles subsidiary plans and baselines and lays down how the project is run, steered and brought to a close.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-management-plan/">Project management plan</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.