Program evaluation and review technique
Definition
The program evaluation and review technique, usually called PERT, estimates the duration of an activity not with a single value but with three: an optimistic, a most likely and a pessimistic one. From these a weighted mean is formed, in which the most likely value counts four times and the sum is divided by six. A measure of spread can also be derived from the range between the pessimistic and optimistic values. The technique originated in the late 1950s in a US Navy weapons programme, where it was also used to analyse entire networks.
Equivalents in other frameworks
Concept Schedule estimation with three values per activity · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | PERT | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Program evaluation and review technique
- Topic area
- Network planning
Distinction
Program evaluation and review technique is the spelled-out PMI term for the method described in the glossary under PERT. It is a particular form of three-point estimating, which can also use a simple average of the three values. More generally, PMI covers estimating with several values under the term multipoint estimating. The critical path method, by contrast, works with a single duration per activity.
In practice
For a data centre migration, the team estimates the night in which the servers are moved: six hours at best, eight most likely, sixteen in the worst case. PERT gives nine hours. The project manager therefore plans a ten-hour maintenance window and warns users in advance that it may be extended.
Frequently asked questions
Why is the most likely value weighted four times?
The weighting goes back to the assumption of a beta distribution of the duration. It ensures that the most likely value shapes the result while extreme values shift it in their direction.
Is PERT worthwhile for every activity?
Usually not. It makes sense for activities with high uncertainty or on the critical path. For well-known routine tasks, a single estimate is generally sufficient.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Program evaluation and review technique. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/program-evaluation-and-review-technique/
Program evaluation and review technique (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/program-evaluation-and-review-technique/ (retrieved 24 November 2026)
@misc{programevaluationandreviewtechnique,
title = {Program evaluation and review technique},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/program-evaluation-and-review-technique/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/program-evaluation-and-review-technique/"> <p>Estimating method that combines optimistic, most likely and pessimistic durations into a weighted value to reflect schedule uncertainty.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/program-evaluation-and-review-technique/">Program evaluation and review technique</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.