Allowance for known risks
The time or budget buffer for identified risks that is used only if they occur; to be distinguished from the management reserve for the unforeseen.
Preferred term
ISO 21506 · 3.79Risk contingency reserve
equivalent
PMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Contingency reserve