Baseline

Definition

The baseline is the frozen, approved version of project planning. It serves as a reference for identifying variances: the current plan may change, while the baseline remains unchanged until a change is formally approved. Separate baselines for scope, schedule and cost are common, and together they make performance measurement possible.

Equivalents in other frameworks

Concept Approved reference version of a plan · three frameworks reviewed

Equivalents of Baseline in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKBaselineequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Baseline

Distinction

The current plan shows how the project is expected to continue, the baseline how it was agreed. A forecast projects the current status into the future. If the baseline is quietly adjusted after every delay, it loses its purpose, because variances no longer become visible.

In practice

After the schedule for refurbishing a data centre has been approved, the project manager saves it as the baseline in the planning tool. From then on, each bar shows two lines: the baseline date and the current date. When the client orders an additional server hall three months later, a new baseline is approved and the old one archived. This keeps it traceable which shifts are due to the change and which to delays.

Frequently asked questions

When may the baseline be changed?

Only after an approved change to scope, schedule or budget, not because of the project's own delays.

Does an agile project need a baseline?

Usually not a fixed detailed plan, but it does need agreed cornerstones such as budget, end date and product goal against which progress is measured.

Source and context

Reference
ISO 21506:2024, 3.4
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Baseline. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/baseline/

Short form

Hain, D. (n.d.): Baseline. PMDecoder, entry on ISO 21506:2024, 3.4. https://pmdecoder.com/en/glossary/baseline/ (retrieved 24 November 2026)

BibTeX
@misc{baseline,
  author  = {Hain, Dennis},
  title   = {Baseline},
  note    = {PMDecoder, ISO 21506:2024, 3.4},
  url     = {https://pmdecoder.com/en/glossary/baseline/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/baseline/">
  <p>Approved version of a plan for scope, schedule or cost against which actual project progress is measured.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/baseline/">Baseline</a>, PMDecoder, ISO 21506:2024, 3.4</footer>
</blockquote>

Found a mistake? Let us know, we check every report.