Project Handbook
Definition
In PM², the Project Handbook describes how a project intends to achieve its objectives. It summarizes the objectives, names critical success factors, sets out the main control processes, escalation and conflict procedures and rules, and records the project's mindsets. It also documents roles and responsibilities, the management plans required and all decisions on tailoring the methodology. The Project Manager drafts it in the Planning Phase, starting from the minutes of the Planning Kick-off Meeting, and keeps it up to date throughout the project. Together with the Project Work Plan, it forms the basis for control and execution.
Equivalents in other frameworks
Concept Comprehensive project management plan · six frameworks reviewed · two false friends
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | Project Plan | false friendno overlap | Despite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level. |
| general | Project plan | false friendno overlap | The project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery. |
| ISO 21506 | Project management plan no entry yet | closely related | contains the management approach and management plans; work breakdown, effort, cost and schedule are in the project work plan |
| ISO 21506 | Project plan | closely related | contains the management approach and management plans; work breakdown, effort, cost and schedule are in the project work plan |
| PMI / PMBOK | Project management plan | closely related | contains the management approach and management plans; work breakdown, effort, cost and schedule are in the project work plan |
| PRINCE2 | Project Initiation Documentation | closely related | Collection of management products that also includes the business case; its approval authorizes the project. |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Project Handbook
- Topic area
- Planning and project structure
Distinction
The Project Handbook governs how the project is managed, while the Project Work Plan contains the work breakdown, effort, costs and schedule. Taken together, the two largely correspond to the project management plan under ISO 21506 or the PMBOK Guide.
In practice
The Project Manager of a laboratory relocation writes in the Project Handbook that risks of medium impact or higher are reported to the Project Steering Committee, that decisions are taken within five working days and that the institute's template is used instead of a separate communication plan. She records this deviation from PM² as a tailoring decision.
Frequently asked questions
Are the management plans part of the Project Handbook?
Yes. The guide recommends treating all project management plans, for example for risks, changes or quality, as part of the Project Handbook.
What happens to the Project Handbook at the end of the project?
It serves as a reference point in the closing meeting, for example to check whether the agreed rules have worked, and is then archived.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitt 6.2
- Edition
- PM² Guide 3.1
Cite this entry
Project Handbook. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-handbook/
Project Handbook (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 6.2. https://pmdecoder.com/en/glossary/project-handbook/ (retrieved 24 November 2026)
@misc{projecthandbook,
title = {Project Handbook},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 6.2},
url = {https://pmdecoder.com/en/glossary/project-handbook/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/project-handbook/"> <p>PM² artefact that brings together a project's management approach, roles, rules, tailoring decisions and all management plans</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-handbook/">Project Handbook</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 6.2</footer> </blockquote>
Found a mistake? Let us know, we check every report.