Monitor & Control

Definition

In PM², Monitor & Control covers all activities used to observe, measure and steer the project work throughout the entire life cycle. The Project Manager compares progress with the plans, detects deviations, decides on corrective actions and deals with risks and issues. The guide divides this area into processes for project performance, schedule, costs, stakeholders, requirements, changes, risks, issues and decisions, quality, deliverables acceptance, transition, business implementation and outsourcing.

Equivalents in other frameworks

Concept Monitoring and controlling a project · three frameworks reviewed

Equivalents of Monitor & Control in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Controlclosely relateddescribed in PM² as a separate group of activities spanning all phases
PRINCE2Progress practiceclosely relatedControl through tolerances and management by exception with fixed escalation levels.
PRINCE2Controlling a stagepartially overlappingControl of a single stage by the Project Manager; Project Board decisions belong to other processes.

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Monitor & Control

Distinction

In the PM² life cycle, Monitor & Control is not a fifth phase in the sequence but runs in parallel with all four phases. The general term project control refers to the same field of tasks; PM² additionally assigns fixed processes, logs and reports to it.

In practice

In an office relocation project, the Project Manager checks dates and costs against the baseline every week, keeps the risk log up to date and decides on minor replanning herself. When the furniture supplier reports a two-week delay, she submits a change request with two alternative dates to the Project Steering Committee.

Frequently asked questions

Is Monitor & Control a separate phase?

No. Although the guide occasionally speaks of a phase, it presents Monitor & Control as a field of activity that accompanies all four phases from beginning to end.

What does the Project Manager work with?

Above all with the Project Work Plan as the baseline, with logs for risks, issues, decisions and changes, and with status and progress reports to the Project Steering Committee.

Source and context

Reference
PM²-Leitfaden 3.1, Abschnitte 3.2.5 und 9
Edition
PM² Guide 3.1
Cite this entry
APA

Monitor & Control. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/monitor-and-control/

Short form

Monitor & Control (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitte 3.2.5 und 9. https://pmdecoder.com/en/glossary/monitor-and-control/ (retrieved 24 November 2026)

BibTeX
@misc{monitorandcontrol,
  title   = {Monitor \& Control},
  note    = {PMDecoder, PM²-Leitfaden 3.1, Abschnitte 3.2.5 und 9},
  url     = {https://pmdecoder.com/en/glossary/monitor-and-control/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/monitor-and-control/">
  <p>In PM², the activities spanning all phases with which the Project Manager measures performance, detects deviations and takes corrective action</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/monitor-and-control/">Monitor &amp; Control</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitte 3.2.5 und 9</footer>
</blockquote>

Found a mistake? Let us know, we check every report.