Initiating Phase
Definition
The Initiating Phase opens the four-phase PM² life cycle. It begins as soon as someone points to an unmet need, a problem or an opportunity, and it ends with the decision on whether the project may move on to planning. During this phase the desired outcomes are described, alignment with the organization's strategy is checked and the foundations for a good start are laid. The central artefacts produced are the Project Initiation Request, the Business Case and the Project Charter; in addition, the first logs for risks, issues and decisions are set up. The driving role in this phase is the Project Owner.
Equivalents in other frameworks
Concept Opening stage of a project · six frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | Initiating a project | closely related | Forms the first management stage and ends with authorization of the project by the Project Board; the pre-project check comes before it. |
| Six Sigma | Define phase | closely related | First phase of an improvement project; more narrowly focused on the problem, a measurable output and customer requirements than general initiation. |
| general | Project initiation | closely related | ends with the Ready for Planning phase gate and delivers the Business Case and Project Charter |
| PRINCE2 | Starting up a project | partially overlapping | Short pre-project check; initiation follows as a separate process. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Initiating Phase
- Topic area
- Initiating
Distinction
The general term project initiation describes the start of a project without fixed artefacts. PM² links the phase to specific documents and roles and closes it with the Ready for Planning phase gate. Detailed plans such as the Project Work Plan do not belong here yet; they are part of the Planning Phase.
In practice
A city administration wants to accept applications for special use of public spaces online. The head of the public order office submits a Project Initiation Request, the Business Manager works through three options in the Business Case, and the Project Manager summarizes scope, milestones and risks in the Project Charter. After six weeks she presents both documents to the Project Steering Committee.
Frequently asked questions
Why should the Initiating Phase not be cut too short?
Teams that start working on deliverables too early often work with unclear objectives. This frequently leads to results that deliver little value and is a common cause of failed projects.
Who decides at the end of the Initiating Phase?
The Project Steering Committee or another Appropriate Governance Body reviews the Business Case and the Project Charter and decides whether the project continues.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitte 3.2.1 und 5
- Edition
- PM² Guide 3.1
Cite this entry
Initiating Phase. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/initiating-phase/
Initiating Phase (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitte 3.2.1 und 5. https://pmdecoder.com/en/glossary/initiating-phase/ (retrieved 24 November 2026)
@misc{initiatingphase,
title = {Initiating Phase},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitte 3.2.1 und 5},
url = {https://pmdecoder.com/en/glossary/initiating-phase/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/initiating-phase/"> <p>First PM² phase, in which a need is turned into project objectives, a Business Case and a Project Charter</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/initiating-phase/">Initiating Phase</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitte 3.2.1 und 5</footer> </blockquote>
Found a mistake? Let us know, we check every report.