Project manager
Definition
The project manager bears operational responsibility for ensuring that a project achieves its agreed objectives. They plan the approach, coordinate the project team, monitor schedule, costs and results and report to the client or a steering committee. Their authority derives from the project mandate and the chosen project organization.
Equivalents in other frameworks
Concept Person responsible for managing a project · five frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Project manager | equivalent | — |
| PRINCE2 | Project Manager (PRINCE2) | closely related | Manages within the Project Board’s tolerances but owns neither the business case nor the decision to continue. |
| PM² | Project Manager | closely related | in PM², explicitly belongs to the Provider Side and reports to the Solution Provider |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Project manager
- Topic area
- Project organization
Distinction
The project manager is not the client: the client commissions the project, provides resources and decides on fundamental changes, while the project manager leads the undertaking within that framework. The role differs from that of a line manager in that its authority to give instructions is usually limited to the project, and disciplinary matters remain with the line organization. In agile frameworks the traditional role is often divided among several roles.
In practice
When a new production line is introduced, an experienced engineer is appointed project manager. Staff from design, purchasing and maintenance contribute their expertise but continue to report to their departments. Crucial to her success is that the project mandate states up to what budget limit she may decide herself and at what point she must involve the steering committee.
Frequently asked questions
What authority does a project manager need?
At a minimum, the right to use resources within the budget, to allocate tasks within the team and to request information from the departments involved. Without these rights, the responsibility comes without the means to exercise it.
Is project manager the same as project management?
Not quite. Project management is the sum of all management tasks in the project; the project manager is the role that carries primary responsibility for them.
Source and context
- Reference
- ISO 21506:2024, 3.67
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Project manager. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-manager/
Hain, D. (n.d.): Project manager. PMDecoder, entry on ISO 21506:2024, 3.67. https://pmdecoder.com/en/glossary/project-manager/ (retrieved 24 November 2026)
@misc{projectmanager,
author = {Hain, Dennis},
title = {Project manager},
note = {PMDecoder, ISO 21506:2024, 3.67},
url = {https://pmdecoder.com/en/glossary/project-manager/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/project-manager/"> <p>Person or position that plans and steers a project on behalf of the client and brings it to completion, with responsibility for its results.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-manager/">Project manager</a>, PMDecoder, ISO 21506:2024, 3.67</footer> </blockquote>
Found a mistake? Let us know, we check every report.