Performance measurement baseline
Definition
In PMI usage, the performance measurement baseline (PMB) combines the scope, schedule and cost baselines into a single approved yardstick. It shows which work is to be done when and with what budget, and is therefore time-phased. Planned value, earned value and actual cost are compared against it. Management reserve is not part of the PMB, whereas contingency reserves for known risks are included in the cost baseline. The PMB is changed only through formal change control, so that variances do not disappear through quiet replanning.
Equivalents in other frameworks
Concept Time-phased baseline for performance measurement · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Performance measurement baseline | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Performance measurement baseline
- Topic area
- Monitoring and control
Distinction
The PMI term is equivalent to the ISO 21506 term of the same name. A single baseline covers only one subject, such as the schedule; the PMB integrates all three. The project budget is larger than the PMB because it also includes the management reserve. The total of the PMB at project end equals the budget at completion.
In practice
For a defence programme, the customer requires earned value management. The project derives twelve control accounts from the work breakdown structure, spreads their budgets across the months of the project and sets the cumulative curve as the PMB. When a design change is approved, the project adjusts the affected control accounts through a documented change request. All others remain unchanged, so the variance reports stay comparable.
Frequently asked questions
Why is management reserve not part of the PMB?
Because it is intended for unforeseen work within scope that cannot yet be assigned to a work package or time period. Only when it is released and allocated to work does the amount move into the PMB.
How often may the PMB be changed?
As rarely as possible, and only for approved changes to scope, schedule or budget. Frequent replanning hides variances and undermines performance measurement.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Performance measurement baseline. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/
Performance measurement baseline (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/ (retrieved 24 November 2026)
@misc{performancemeasurementbaselinepmi,
title = {Performance measurement baseline},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/"> <p>Combined baseline of scope, schedule and cost that serves as the yardstick for measuring project performance.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/">Performance measurement baseline</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.