Trend analysis
Definition
In trend analysis, values such as dates, costs, percent complete or defect counts are examined across several points in time. The course of the values shows whether a quantity remains stable, improves or deteriorates, and where it is heading if the development continues unchanged. This makes problems visible before they show up in a single plan-versus-actual comparison.
Equivalents in other frameworks
Concept Evaluating development across several data dates · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Trend analysis | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Other terms
Other words for the same thing in English usage. Not to be confused with the equivalents above, which translate between frameworks.
- Milestone trend analysis
- related, not equivalent
- MTA
- related, not equivalent
Classification
- this term
- Trend analysis
- Topic area
- Monitoring and control
Distinction
Variance analysis looks at one point in time, trend analysis at a series. Milestone trend analysis is a common special form in which the currently expected dates of milestones are plotted in a chart across the reporting dates. A forecast can be based on a trend analysis but often uses further information.
In practice
In a construction project, the project manager estimates each month the expected completion date for the structural shell. In the milestone trend analysis chart, the line rises slightly three months in a row, although each individual slip amounts to only a few days. The project manager treats this as a warning sign and clarifies the staffing situation with the shell construction contractor. The cause is a shortage of formwork carpenters, which is remedied with a subcontractor.
Frequently asked questions
How do you read a milestone trend analysis?
Horizontal lines mean stable dates, rising lines slips to later dates, falling lines improvements. If many lines rise at the same time, this points to a fundamental planning problem.
How many data points does a trend analysis need?
It becomes meaningful from about three to four measurements. It is important that the values are always collected in the same way.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Trend analysis. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/trend-analysis/
Hain, D. (n.d.): Trend analysis. PMDecoder. https://pmdecoder.com/en/glossary/trend-analysis/ (retrieved 24 November 2026)
@misc{trendanalysis,
author = {Hain, Dennis},
title = {Trend analysis},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/trend-analysis/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/trend-analysis/"> <p>Evaluation of how project metrics develop over several reporting dates in order to detect future variances early</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/trend-analysis/">Trend analysis</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.