Predecessor activity
Definition
A predecessor activity is an activity on which another activity in the schedule logically depends. Through the logical relationship, usually finish-to-start, the predecessor determines when the dependent activity can start or finish at the earliest. An activity can have several predecessors; in the forward pass, the one that produces the latest date for the successor then governs. Being a predecessor is always relative: the same activity is at the same time a successor with respect to another. Usually only the project start has no predecessor.
Equivalents in other frameworks
Concept Activity on which another depends · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Predecessor activity | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Predecessor activity
- Topic area
- Network planning
Distinction
The predecessor activity corresponds to the German Vorgänger in network planning. Its counterpart is the successor activity. An activity that occurs earlier in time is not automatically a predecessor; only a defined logical relationship makes it one. Conversely, a predecessor may run in parallel, for example with start-to-start.
In practice
In an IT project, approval of the functional specification is the predecessor of three activities: programming, test case preparation and licence procurement. When the approval is delayed by a week, the scheduling tool immediately shows that all three successors start later, but that licence procurement has no impact on the project end because of its float.
Frequently asked questions
How many predecessors should an activity have?
As many as the actual logic of the work requires. What matters is that every activity except the project start has at least one predecessor so that delays are passed on correctly.
Can a milestone be a predecessor?
Yes. A milestone such as an approval is often the predecessor of activities that may only start after that decision.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Predecessor activity. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/predecessor-activity-pmi/
Predecessor activity (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/predecessor-activity-pmi/ (retrieved 24 November 2026)
@misc{predecessoractivitypmi,
title = {Predecessor activity},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/predecessor-activity-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/predecessor-activity-pmi/"> <p>In a schedule, the activity on which a dependent activity logically relies and whose timing shapes that activity's dates.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/predecessor-activity-pmi/">Predecessor activity</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.