Start-to-finish relationship
abbr. SF
Definition
A start-to-finish relationship links the start of a predecessor to the finish of a successor. The successor may therefore only be completed once the predecessor has started. This seems counter-intuitive at first, but it describes handovers well: an old system is only to be switched off once the new one has gone live.
Equivalents in other frameworks
Concept Finish after another activity starts · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Start-to-finish | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- Broader term
- Logical relationship
- this term
- Start-to-finish relationship
- Topic area
- Network planning
Distinction
The start-to-finish relationship is the rarest of the four logical relationships. Many schedulers avoid it because it is hard to read, and they represent the same logic with a milestone and finish-to-start relationships. Unlike a finish-to-start relationship, it is not the start but the finish of the successor that waits for the predecessor.
In practice
A municipal utility is moving customer billing to a new system. The activity "Operate legacy system" may only finish once "Operate new system" has started, so that there is no gap in billing. The planner uses a start-to-finish relationship for this. If the start of the new system slips by a month, operation of the legacy system is extended automatically, and the licence costs for that month appear in the plan.
Frequently asked questions
How is the start-to-finish relationship abbreviated?
In English as SF. In German, it is also abbreviated as SF (Sprungfolge), and in German-language scheduling software often as AE (Anfang-Ende).
Should start-to-finish relationships be used?
Only where they clearly represent a handover. A milestone such as "New system live" with two finish-to-start relationships is often easier to understand.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Start-to-finish relationship. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/start-to-finish-relationship/
Hain, D. (n.d.): Start-to-finish relationship. PMDecoder. https://pmdecoder.com/en/glossary/start-to-finish-relationship/ (retrieved 24 November 2026)
@misc{starttofinishrelationship,
author = {Hain, Dennis},
title = {Start-to-finish relationship},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/start-to-finish-relationship/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/start-to-finish-relationship/"> <p>Rarely used logical relationship in which an activity can finish at the earliest once another activity has started</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/start-to-finish-relationship/">Start-to-finish relationship</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.