Checkpoint Report
Definition
In PRINCE2 the Checkpoint Report is the regular report on the progress of a work package. The Team Manager carrying out the work package prepares it for the Project Manager. The frequency and format of reporting are agreed when the work package is handed over. The report states the reporting period, the products completed and started during that time, the quality checks carried out, the plans for the next period, the position against the work package tolerances, and any problems and risks that have arisen. It need not be written; a short conversation at a fixed time can serve as a checkpoint as long as the agreed information is passed on. The Project Manager reviews the reports and feeds the results into his or her own reporting.
Equivalents in other frameworks
Concept Regular project status report · two frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Progress report | partially overlapping | Progress report at work package level from the Team Manager to the Project Manager. |
| PM² | Project Progress Report | partially overlapping | Progress report at work package level from the Team Manager to the Project Manager. |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Checkpoint Report
- Topic area
- Stakeholders and communication
Distinction
The Checkpoint Report sits at the delivery level: it flows from the team to the Project Manager. The Highlight Report sits one level higher and reports from the Project Manager to the Project Board on the whole stage. A generic progress report in ISO 21506 may refer to either level. If a work package is forecast to exceed its tolerances, the Checkpoint Report is not enough; the Team Manager then raises an issue with the Project Manager.
In practice
An external supplier is developing the claims notification module for an insurance company. A weekly checkpoint has been agreed in the work package. Every Friday the supplier’s team leader sends a one-page report: two screens finished and tested, the interface to policy administration started, one test postponed because test data are missing. The Project Manager records the missing test data in the Daily Log and resolves the matter with the business department.
Frequently asked questions
Does a Checkpoint Report have to be written?
No. Format and frequency are agreed in the work package. A short meeting or conference call is sufficient if the agreed information is passed on and recorded where necessary.
Who receives the Checkpoint Report?
The Project Manager. The Project Board does not normally see the individual reports; it receives a summary for the whole stage through the Highlight Report.
Source and context
- Reference
- PRINCE2 7, Praktik Fortschritt
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Checkpoint Report. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/checkpoint-report/
Hain, D. (n.d.): Checkpoint Report. PMDecoder, entry on PRINCE2 7, Praktik Fortschritt. https://pmdecoder.com/en/glossary/checkpoint-report/ (retrieved 24 November 2026)
@misc{checkpointreport,
author = {Hain, Dennis},
title = {Checkpoint Report},
note = {PMDecoder, PRINCE2 7, Praktik Fortschritt},
url = {https://pmdecoder.com/en/glossary/checkpoint-report/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/checkpoint-report/"> <p>PRINCE2 progress report from a Team Manager to the Project Manager on the status of a work package, produced at agreed intervals.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/checkpoint-report/">Checkpoint Report</a>, PMDecoder, PRINCE2 7, Praktik Fortschritt</footer> </blockquote>
Found a mistake? Let us know, we check every report.