Estimate at completion
Definition
At PMI, the estimate at completion, abbreviated EAC, is the total of all costs expected, as of the data date, to be incurred by the time the work is completed. It is made up of the actual cost so far and the estimate to complete for the remaining work. PMI describes several ways of calculating it: a new bottom-up estimate of the remaining work, the assumption that the remaining work will proceed as budgeted, extrapolation with the current CPI (EAC = BAC / CPI) or extrapolation with both CPI and SPI. Which approach fits depends on whether the efficiency to date is expected to continue.
Equivalents in other frameworks
Concept Expected total cost at completion · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Estimate at completion | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Estimate at completion
- Topic area
- Monitoring and control
Distinction
The PMI term is equivalent to “Schätzung bei Fertigstellung” (estimate at completion) according to ISO 21506, the lead term of the concept in the glossary. The budget at completion is the approved plan, the EAC the current expectation. The estimate to complete covers only the remaining cost. The difference between BAC and EAC is the variance at completion.
In practice
A project with a BAC of 1.2 million euros has a CPI of 0.92 after half of the work. Extrapolation gives an EAC of around 1.3 million euros. The team considers the causes, costly onboarding of external staff, to have been overcome and re-estimates the remaining work. This bottom-up estimate comes to 1.25 million euros, which is reported to the steering committee as the forecast.
Frequently asked questions
Which EAC formula is the right one?
None is right in general. Extrapolating with the CPI assumes unchanged efficiency; assuming budgeted remaining work assumes that past variances were one-offs. The choice should be justified and stated in the report.
How often is the estimate at completion updated?
In every reporting period in which earned value data is collected. It is important to track its development over time, because a steadily rising EAC points to a systematic problem.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Estimate at completion. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/estimate-at-completion-pmi/
Estimate at completion (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/estimate-at-completion-pmi/ (retrieved 24 November 2026)
@misc{estimateatcompletionpmi,
title = {Estimate at completion},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/estimate-at-completion-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/estimate-at-completion-pmi/"> <p>Forecast of total cost at project end: costs incurred so far plus the expected cost of the remaining work (EAC = AC + ETC).</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/estimate-at-completion-pmi/">Estimate at completion</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.