Issues practice

Definition

The issues practice governs how a PRINCE2 project deals with anything unplanned that needs attention. This includes, for example, requests to change an agreed product, deviations of a product from its specification, and other problems and concerns. Each item is captured, assessed, brought to a decision at the appropriate level and followed up. The practice also covers keeping the status of products and their versions traceable so that changes are made in a controlled way. How this is done in the individual project is described in the issue management approach. The practice replaces the change theme of the 2017 edition and takes a broader view of its subject.

Equivalents in other frameworks

Concept Controlled handling of changes · two frameworks reviewed

Equivalents of Issues practice in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKChange controlclosely relatedemphasizes the review of and decision on change requests, less their implementation
generalChange controlclosely relatedCovers not only change requests but also deviations from specification, problems and concerns.

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Other terms

Other words for the same thing in English usage. Not to be confused with the equivalents above, which translate between frameworks.

Change theme
deprecated

Classification

this term
Issues practice

Distinction

A risk is an uncertain event that may occur; an issue has already occurred or has been raised as a concern. General change management deals with change requests; the issues practice also covers problems, complaints and defects. The issue register under ISO 21506 is a tool, whereas the practice describes the handling as a whole.

In practice

In a project introducing a new till system, a branch manager reports that vouchers cannot be scanned. The project manager records this as a deviation from the specification and assesses the consequences. Because the fix is possible within the tolerances of the current stage, she decides herself. A second request, to integrate loyalty cards, would break the budget; she refers it to the project board.

Frequently asked questions

Who decides on change requests?

In principle, the project board. It can delegate decisions up to an agreed limit to a change authority or to the project manager; this arrangement is recorded in the issue management approach.

Does every issue have to be recorded formally?

No. The project manager can also resolve minor points informally and simply note them. What needs assessment, a decision or follow-up is recorded formally.

Source and context

Reference
PRINCE2 7, Praktik Issues
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Issues practice. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/issues-practice/

Short form

Hain, D. (n.d.): Issues practice. PMDecoder, entry on PRINCE2 7, Praktik Issues. https://pmdecoder.com/en/glossary/issues-practice/ (retrieved 24 November 2026)

BibTeX
@misc{issuespractice,
  author  = {Hain, Dennis},
  title   = {Issues practice},
  note    = {PMDecoder, PRINCE2 7, Praktik Issues},
  url     = {https://pmdecoder.com/en/glossary/issues-practice/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/issues-practice/">
  <p>PRINCE2 7 practice for handling unplanned events, change requests and deviations that require a decision.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/issues-practice/">Issues practice</a>, PMDecoder, PRINCE2 7, Praktik Issues</footer>
</blockquote>

Found a mistake? Let us know, we check every report.