Resources and estimating
Terms for resources and estimating: planning demand and capacity, levelling resources and estimating effort, duration or cost with suitable methods.
- Analogous estimatingcross-frameworkEstimating technique that derives effort, duration or cost from the actual values of a comparable earlier project
- Analogous estimatingPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Estimation of duration or cost that takes the recorded figures of a comparable earlier activity or project as its reference point.
- Basis of estimateISO 21506 · 3.5Record of the data, assumptions and methods on which an estimate of what the planned activities will need is based.
- Bottom-up estimatingcross-frameworkEstimating technique in which individual work packages or activities are estimated and the values added up to an overall estimate
- Bottom-up estimatingPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Estimation that begins with figures for the smallest units of work and rolls them up level by level into totals for duration or cost.
- Brooks's lawcross-frameworkRule of thumb stating that adding staff to a software project that is already late delays it further
- EffortPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Amount of work, in person-hours or person-days, that an activity requires, regardless of how many calendar days it is spread over.
- Effort estimationcross-frameworkForward-looking determination of the effort, duration or cost of an undertaking on the basis of available information and experience
- Expert judgementcross-frameworkAssessment by people with particular expertise or experience, used in planning, estimating and decision-making in a project
- Expert judgmentPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Judgment based on expertise in an application area, discipline or industry that is used for a project task.
- Historical datacross-frameworkRecorded information from completed projects used for estimating, planning and risk assessment in new undertakings
- Multipoint estimatingPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Estimation that captures uncertainty with three values, optimistic, most likely and pessimistic, and derives an expected value from them.
- Parametric estimatingcross-frameworkEstimating technique that calculates effort or cost from an established relationship between unit rates and quantities
- Parametric estimatingPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Estimation that extrapolates cost or duration from historical figures, for example cost per square metre times floor area, or via a regression model.
- Resourcecross-frameworkStaff, equipment, materials, facilities or funds that a project needs to carry out its work and that are planned for it
- Resource breakdown structureISO 21506 · 3.74Hierarchical breakdown of the resources needed in a project by type, such as staff by qualification, equipment and materials.
- Resource breakdown structurePMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Tree-like ordering of all resources a project needs, such as staff, material, equipment and services, broken down into finer kinds.
- Resource histogramcross-frameworkColumn chart showing the planned demand for a resource per time period, often compared with the available capacity
- Resource levelingPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Adjusting start and finish dates so that resource demand matches the available capacity.
- Resource levellingcross-frameworkAdjusting a schedule so that no resource is planned beyond its available capacity
- Resource loadingISO 21506 · 3.73Determining which people, equipment, materials and other means the planned work of an undertaking needs, and when.
- Resource management planPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Subsidiary plan for dealing with the team and physical resources, from determining needs and acquiring them to tracking their use.
- Resource planningcross-frameworkDetermining which resources a project needs, when and to what extent, and matching this demand against the available capacity
- Three-point estimatingcross-frameworkEstimating technique that collects an optimistic, a most likely and a pessimistic value and derives an expected value from them
- Time recordingcross-frameworkRecording the working time that employees spend on projects, work packages or tasks
- Work effortcross-frameworkAmount of working time that an activity or work package requires, measured in person-hours or person-days
Concepts in this topic area
- Adjusting the schedule to available capacityThe shifting or stretching of activities so that no resource is scheduled beyond its available capacity, if necessary with a later project end.Resource levelling · Resource leveling
- Amount of labour a task requiresThe working time an activity or work package requires, in person-hours or person-days; with several people, the duration is shorter than the effort.Work effort · Effort
- Determining resource needs and deploymentThe determination of which people, equipment and materials a project needs, when and to what extent, and their alignment with the available capacity.Resource planning · Resource management plan
- Estimating from comparable initiativesThe estimating technique that derives effort, duration or cost from the actual values of similar past initiatives; fast, but only as good as the comparison.Analogous estimating · Analogous estimating
- Estimating from the bottom upThe estimating technique that estimates individual work packages or activities and adds the values up to total effort and cost; accurate but time-consuming.Bottom-up estimating · Bottom-up estimating
- Estimating using statistical parametersThe estimating technique that calculates effort or cost from an established relationship, such as cost per square metre or hours per function.Parametric estimating · Parametric estimating
- Estimating with several values per quantityThe estimating technique that combines optimistic, most likely and pessimistic values to make uncertainty visible and form an expected value.Three-point estimating · Multipoint estimating
- Hierarchical breakdown of resourcesThe tree-like breakdown of the resources needed in a project by type and category, such as staff, material and equipment, for planning and analysis.Resource breakdown structure · Resource breakdown structure
- Judgement by expertsThe judgement of people with particular expertise or experience, which is drawn upon in planning, estimating, risk analysis and decision-making.Expert judgement · Expert judgment