Topic area

Resources and estimating

Terms for resources and estimating: planning demand and capacity, levelling resources and estimating effort, duration or cost with suitable methods.

26 terms

Concepts in this topic area

  • Adjusting the schedule to available capacityThe shifting or stretching of activities so that no resource is scheduled beyond its available capacity, if necessary with a later project end.Resource levelling · Resource leveling
  • Amount of labour a task requiresThe working time an activity or work package requires, in person-hours or person-days; with several people, the duration is shorter than the effort.Work effort · Effort
  • Determining resource needs and deploymentThe determination of which people, equipment and materials a project needs, when and to what extent, and their alignment with the available capacity.Resource planning · Resource management plan
  • Estimating from comparable initiativesThe estimating technique that derives effort, duration or cost from the actual values of similar past initiatives; fast, but only as good as the comparison.Analogous estimating · Analogous estimating
  • Estimating from the bottom upThe estimating technique that estimates individual work packages or activities and adds the values up to total effort and cost; accurate but time-consuming.Bottom-up estimating · Bottom-up estimating
  • Estimating using statistical parametersThe estimating technique that calculates effort or cost from an established relationship, such as cost per square metre or hours per function.Parametric estimating · Parametric estimating
  • Estimating with several values per quantityThe estimating technique that combines optimistic, most likely and pessimistic values to make uncertainty visible and form an expected value.Three-point estimating · Multipoint estimating
  • Hierarchical breakdown of resourcesThe tree-like breakdown of the resources needed in a project by type and category, such as staff, material and equipment, for planning and analysis.Resource breakdown structure · Resource breakdown structure
  • Judgement by expertsThe judgement of people with particular expertise or experience, which is drawn upon in planning, estimating, risk analysis and decision-making.Expert judgement · Expert judgment

All concepts compared