Terms for planning and structuring a project: decomposition, breakdown structures, assumptions, constraints, dependencies and the project management plan.
- 100 % ruleISO 21506 · 3.1Principle for work breakdown structures: the elements directly below an element together cover exactly all of its work, no more and no less.
- AssumptionPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)In PMI usage, something the planning treats as given even though it has not yet been confirmed or proven.
- Bill of materialscross-frameworkStructured list of all components, assemblies and materials that make up a product, with quantities and identifiers
- Code of accountsPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Numbering scheme that assigns every WBS element a distinct identifier such as 1.2.3, making costs and dates traceable to it.
- Constraintcross-frameworkFixed condition that limits a project's room for manoeuvre, such as a fixed date, a budget cap or an official requirement
- ConstraintPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Limit or requirement, such as a fixed deadline, a capped budget or a regulation, that narrows the options for carrying out an undertaking.
- DecompositionISO 21506 · 3.19Step-by-step refinement of an undertaking into smaller parts that are easier to plan and control, repeated as more detail becomes known.
- DecompositionPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Technique for breaking a large scope of work or deliverables down level by level until parts emerge that can be estimated and controlled.
- Dependencycross-frameworkRelationship in which an activity, result or project relies on another in order to start or finish
- DependencyPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)In PMI usage, a relationship in which one activity, result or project relies on another, usually modelled as a logical relationship.
- Hierarchical decompositionISO 21506 · 3.29Top-down breakdown of the scope of a project or programme, level by level, until manageable elements of the work breakdown structure emerge.
- Parent elementISO 21506 · 3.43Element of a work breakdown structure whose work has been split into at least two elements on the level below.
- Planning assumptioncross-frameworkCircumstance taken as given for planning purposes without yet being reliably confirmed
- Plans practicePRINCE2 · Praktik PlänePRINCE2 7 practice describing how plans are prepared at several levels, starting from the products to be delivered.
- Product BacklogScrum · Abschnitt Product BacklogOrdered, continuously evolving list of all work intended to improve a product, and the Scrum Team's single source of work
- Product breakdown structureISO 21506 · 3.53Hierarchical breakdown of a project's result into its sub-products and components.
- Product Breakdown StructurePRINCE2 · Praktik PläneHierarchical breakdown of all products of a plan in PRINCE2, the starting point of product-based planning.
- Product DescriptionPRINCE2 · ManagementproduktePRINCE2 management product describing the purpose, composition, quality criteria and checking methods of a single product.
- Project HandbookPM² · Abschnitt 6.2PM² artefact that brings together a project's management approach, roles, rules, tailoring decisions and all management plans
- Project Initiation DocumentationPRINCE2 · ManagementprodukteSet of PRINCE2 management products defining the project; the project board authorizes the project by approving it.
- Project management planISO 21506no entry yet
- Project management planPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Central planning document of a project that bundles subsidiary plans and baselines and lays down how the project is run, steered and brought to a close.
- Project plancross-frameworkIn everyday usage usually the schedule; in the PMBOK Guide, by contrast, a far more comprehensive document.
- Project planISO 21506 · 3.68Under ISO 21506, the binding document that brings together a project's technical baselines and its management baselines.
- Project PlanPRINCE2 · Praktik PlänePRINCE2 plan showing for the whole project which major products are delivered when, with which resources and at what cost.
- Project planningcross-frameworkWorking out the path to the project result, covering scope, sequence, dates, resources, costs, risks and organization
- Rolling wave planningISO 21506 · 3.82Planning approach in which near-term stages are planned in detail and later ones only roughly, with detail added step by step.
- Rolling wave planningPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Planning in stages: work due soon is detailed now, while later work is sketched roughly and refined as it approaches.
- Subprojectcross-frameworkClearly defined part of a larger project with its own lead and objectives, contributing to the overall project
- WBS codecross-frameworkUnique, usually hierarchical number assigned to each element of the work breakdown structure
- WBS dictionaryPMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Companion document to the WBS that explains every element in detail, including its content, dates and responsible party.
- Work breakdown structureISO 21506 · 3.96Hierarchical decomposition of the entire project scope into ever smaller components, down to the work package.
- Work breakdown structurePMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Deliverable-oriented breakdown of the entire project scope into levels down to work packages that together cover exactly this scope.
- Work breakdown structure dictionaryISO 21506 · 3.97Companion document to the work breakdown structure that records, element by element, content, results, responsibility and other details.
- Work breakdown structure elementISO 21506 · 3.98Any individual building block of the work breakdown structure at a particular level, from the top element down to the work package.
- Work packageISO 21506 · 3.99 und 3.100Defined unit of related activities at the lowest level of the work breakdown structure, with its own result, timeframe and budget.
- Work packagePMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Smallest unit in the WBS: a clearly bounded partial result with one owner, for which effort, cost and duration are planned.
- Work PackagePRINCE2 · ManagementprodukteIn PRINCE2, the agreed transfer of responsibility for delivering specific products from the project manager to a team manager.
- Work package descriptioncross-frameworkDocument that bindingly records the content, results, responsible person, dates, effort and interfaces of a work package
Concepts in this topic area
- Circumstance assumed true for planningA circumstance that is assumed to be true for planning without being certain; assumptions are documented and reviewed as the project proceeds.Planning assumption · Assumption
- Comprehensive project management planThe overall document that sets out how a project is planned, executed, monitored and closed, bringing together all subsidiary plans from scope to communication.Project management plan · Project plan · Project management plan · Project Initiation Documentation · Project Handbook · Project Plan · Project plan
- Description of work breakdown structure elementsThe companion document to the work breakdown structure that describes the content, results, responsible parties, dates and effort for each of its elements.Work breakdown structure dictionary · WBS dictionary · Product Description · Work package description
- Fixed limitation on the options availableA fixed limitation, such as a budget cap, a deadline or a standard, that must be observed in all planning and solution decisions throughout the project.Constraint · Constraint
- Hierarchical decomposition of project scopeThe step-by-step breakdown of the entire project scope into ever smaller, manageable units until plannable work packages with clear responsibility emerge.Work breakdown structure · Work breakdown structure · Product breakdown structure · Product Breakdown Structure · Product Backlog
- Identifier of work breakdown structure elementsThe unique, usually hierarchical number that identifies each element of the work breakdown structure and links it in cost and schedule planning.WBS code · Code of accounts
- Progressively refined planningThe planning approach in which near-term stages are planned in detail and later ones only roughly; the plan is continually refined as knowledge grows.Rolling wave planning · Rolling wave planning
- Reliance on another elementThe relationship in which an activity, result or project relies on another in order to start or finish, whether within or outside the project itself.Dependency · Dependency
- Smallest planning unit of the project structureThe lowest level of the work breakdown structure, for which effort, costs, dates and responsibility are planned and whose progress is measured.Work package · Work package · Work Package
- Stepwise division into smaller unitsThe planning technique that divides the scope and results of a project into smaller parts until they can be estimated, planned and assigned.Decomposition · Decomposition
- Working out the path to the project resultWorking out the path to the project result: scope, sequence, dates, resources, costs, risks and organization, starting from the deliverables required.Project planning · Plans practice