Earned value
also: Budgeted cost of work performed · abbr. EV, BCWP
Definition
Earned value answers the question of how much of the planned work has already been done and expresses the answer in money. For each work package, the progress achieved is valued at its budget, and the results are added up across all packages. Because it uses the same unit as planned value and actual cost, it can be compared directly with both, which makes it the central figure of earned value management.
Equivalents in other frameworks
Concept Value of work performed · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Earned value | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Earned value
- Topic area
- Monitoring and control
Distinction
Planned value shows which work should have been done by the cut-off date, earned value which work has been done, and actual cost what that work cost. It is closely linked to percent complete: the percentage expresses progress, earned value is the amount calculated from it. The PMBOK Guide uses the same figure under the same name.
In practice
A software company has budgeted ten work packages totalling 400,000 euros for a customer portal. After three months, four packages worth 150,000 euros are complete, and a fifth worth 60,000 euros counts as half done under the agreed 50/50 rule. Earned value is therefore 180,000 euros. Planned value was 200,000 euros and actual cost 170,000 euros: the project is behind schedule but spending less than budgeted.
Frequently asked questions
How is progress measured for earned value?
Using rules agreed before work starts, such as 0/100 (credited only on completion), 50/50 (half credited at the start) or progress by completed interim milestones. Subjective percentage estimates are considered error-prone.
Can earned value exceed the budget?
Not beyond the budget at completion. Once all the work is done, earned value equals exactly that budget, regardless of what the work actually cost.
Source and context
- Reference
- ISO 21506:2024, 3.21
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Earned value. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/earned-value-iso/
Hain, D. (n.d.): Earned value. PMDecoder, entry on ISO 21506:2024, 3.21. https://pmdecoder.com/en/glossary/earned-value-iso/ (retrieved 24 November 2026)
@misc{earnedvalueiso,
author = {Hain, Dennis},
title = {Earned value},
note = {PMDecoder, ISO 21506:2024, 3.21},
url = {https://pmdecoder.com/en/glossary/earned-value-iso/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/earned-value-iso/"> <p>Monetary value of the work actually finished by a cut-off date, measured with the budget that was planned for that work.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/earned-value-iso/">Earned value</a>, PMDecoder, ISO 21506:2024, 3.21</footer> </blockquote>
Found a mistake? Let us know, we check every report.