Critical chain method

Definition

The critical chain method is a scheduling approach that considers the availability of scarce resources as well as logical dependencies. The longest chain of activities resulting from logic and resource constraints is called the critical chain. Activity durations are estimated tightly, without the safety margins that are otherwise built into each individual estimate. That reserve is pooled instead: as a project buffer at the end of the critical chain and as feeding buffers where other paths join the critical chain. Control is based on how much buffer has been consumed relative to progress. The method goes back to Eliyahu M. Goldratt and is based on his theory of constraints.

Equivalents in other frameworks

Concept Scheduling with aggregated buffers · three frameworks reviewed

Equivalents of Critical chain method in other frameworks
FrameworkTerm thereRelationNote
generalCritical chain methodequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Critical chain method

Distinction

The critical chain method corresponds to the German Methode der kritischen Kette. The critical path method initially looks only at logic and deals with resources in a separate step; its float is calculated flexibility of individual activities. In critical chain, buffers are deliberately planned and managed reserves. A schedule buffer in the general sense is any planned time reserve, whatever the method.

In practice

In product development at a device manufacturer, the test laboratory is a bottleneck shared by several projects. The project manager plans the laboratory tests as part of the critical chain, cuts the teams' estimates to realistic values without margins and places a four-week project buffer before the launch date. The weekly meetings then focus on just two questions: how much buffer has been used, and how much work on the chain is still open.

Frequently asked questions

Why is safety time removed from individual estimates?

Experience shows that distributed reserves are often lost, because work expands to fill the available time or is started late. A shared buffer balances delays and early finishes of individual activities and can therefore be smaller overall.

When is the critical chain method suitable?

Mainly when a few scarce resources determine the flow of work, such as specialists, test rigs or equipment, and when those involved are willing to work with tight estimates and open buffer monitoring.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Critical chain method. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/critical-chain-method-pmi/

Short form

Critical chain method (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/critical-chain-method-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{criticalchainmethodpmi,
  title   = {Critical chain method},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/critical-chain-method-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/critical-chain-method-pmi/">
  <p>Scheduling method that accounts for scarce resources and pools safety time into shared buffers on paths.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/critical-chain-method-pmi/">Critical chain method</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.