Business case
Definition
In PMI usage, the business case is a documented economic feasibility assessment used to establish the expected benefits of an undertaking that is not yet fully defined. It describes the trigger or problem, compares alternative courses of action, estimates costs, benefits and risks, and makes a recommendation. On this basis the organization decides whether to authorize the undertaking. PMI counts the business case among a project's business documents, which are owned outside the project and should remain valid throughout the life cycle.
Equivalents in other frameworks
Concept Economic justification of an initiative · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Business case | equivalent | — |
| PRINCE2 | Business Case | equivalent | In PRINCE2 kept up to date throughout the project and checked at every stage boundary. |
| PRINCE2 | Continued business justification | partially overlapping | Principle of reviewing the justification throughout the project; the document itself is the business case. |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Business case
- Topic area
- Initiating
Distinction
The term corresponds to the business case in the standard. A feasibility analysis examines whether an undertaking can be carried out at all and may provide input to the business case. The benefits management plan describes how the benefits promised in the business case are achieved and measured. The project charter authorizes the project and relies on the business case, but does not replace it.
In practice
A brewery is considering its own photovoltaic system. The business case compares three options: continuing to buy electricity, a rooftop system and a ground-mounted system with storage. For each, it sets out the investment, operating costs, savings over twenty years and risks such as electricity price trends and permits. Management chooses the rooftop system, and the business case becomes the basis for the project charter.
Frequently asked questions
Who is responsible for the business case?
Usually the sponsor or the responsible business side, not the project manager. The project manager may help to prepare it and reports when assumptions prove wrong during the project.
Is the business case reviewed during the project?
Yes, at least at key decision points. If the justification no longer holds, for instance because costs rise sharply or the benefits disappear, a decision must be made to adjust or terminate the undertaking.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Business case. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/business-case-pmi/
Business case (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/business-case-pmi/ (retrieved 24 November 2026)
@misc{businesscasepmi,
title = {Business case},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/business-case-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/business-case-pmi/"> <p>Documented assessment of benefits, costs and risks that serves as the basis for deciding on an undertaking.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/business-case-pmi/">Business case</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.