Resource breakdown structure
Definition
The resource breakdown structure arranges all of a project's resources in a tree structure. The top level contains categories such as staff, machinery, materials and services, with finer groups below, such as electricians, cranes or concrete grades. The breakdown makes it easier to plan requirements, analyse costs by resource type and identify bottlenecks across several work packages.
Equivalents in other frameworks
Concept Hierarchical breakdown of resources · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Resource breakdown structure | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Resource breakdown structure
- Topic area
- Resources and estimating
Distinction
The work breakdown structure breaks down the work, the resource breakdown structure the means used to carry it out. An organization chart shows people and reporting lines, the resource breakdown structure types and qualifications regardless of names. A bill of materials breaks a product down into its components, not the resources used to make it.
In practice
An event technology company is planning a music festival with three stages. The resource breakdown structure divides staff into sound, lighting, rigging and stage construction, each with qualification levels, and equipment into loudspeakers, lighting desks, trusses and generators. The analysis shows that certified riggers are needed on all three stages at the same time and that the company's own pool is not large enough. Two riggers are booked externally at an early stage.
Frequently asked questions
How detailed should the resource breakdown structure be?
As detailed as resources are actually planned and procured differently. Qualifications that can substitute for each other form a single group.
What is it used for in practice?
For requirements and capacity planning, for cost analyses by resource type and as a standard list in planning tools.
Source and context
- Reference
- ISO 21506:2024, 3.74
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Resource breakdown structure. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/resource-breakdown-structure/
Hain, D. (n.d.): Resource breakdown structure. PMDecoder, entry on ISO 21506:2024, 3.74. https://pmdecoder.com/en/glossary/resource-breakdown-structure/ (retrieved 24 November 2026)
@misc{resourcebreakdownstructure,
author = {Hain, Dennis},
title = {Resource breakdown structure},
note = {PMDecoder, ISO 21506:2024, 3.74},
url = {https://pmdecoder.com/en/glossary/resource-breakdown-structure/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/resource-breakdown-structure/"> <p>Hierarchical breakdown of the resources needed in a project by type, such as staff by qualification, equipment and materials.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/resource-breakdown-structure/">Resource breakdown structure</a>, PMDecoder, ISO 21506:2024, 3.74</footer> </blockquote>
Found a mistake? Let us know, we check every report.