Solution Provider
abbr. SP
Definition
In PM², the Solution Provider (SP) represents those who design, build, implement or outsource the results of a project. The role is ultimately accountable for the deliverables that the Project Owner has asked for, provides the resources of the delivering organization and names the Project Manager. If parts of the project are outsourced, the Solution Provider approves their objectives and is accountable for the contractors' performance. The role is usually held by a manager of the delivering unit who works closely with the Project Owner on the business objectives.
Equivalents in other frameworks
Concept Leading role of the delivering side · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | Senior Supplier | closely related | May represent several internal and external suppliers; the project manager is appointed by the Executive, not by the Senior Supplier. |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
All designations of this concept side by side
Comparisons
Classification
- this term
- Solution Provider
- Topic area
- Project organization
Distinction
In PM², the Solution Provider belongs to the organization itself and is not an external contractor; for external companies there is the role of the contractor's project manager. In relation to the Project Manager, the Solution Provider is the higher, directing authority and does not plan or coordinate the work.
In practice
For a new document management system in an agency, the head of the IT department is the Solution Provider. He assigns three developers and a tester, appoints an experienced Project Manager and outsources the data migration to a service provider. When that provider's delivery arrives two weeks late, he settles the consequences with the provider and reports to the Project Steering Committee.
Frequently asked questions
Can the Solution Provider also act as Project Manager?
PM² deliberately separates the two roles: the Solution Provider directs and provides resources, while the Project Manager coordinates the daily work. In small organizations tailoring may be necessary, which is then documented in the Project Handbook.
When is the Solution Provider appointed?
Already in the Initiating Phase, as soon as it is clear which organizational unit will carry out the project.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitt 4.6
- Edition
- PM² Guide 3.1
Cite this entry
Solution Provider. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/solution-provider/
Solution Provider (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 4.6. https://pmdecoder.com/en/glossary/solution-provider/ (retrieved 24 November 2026)
@misc{solutionprovider,
title = {Solution Provider},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.6},
url = {https://pmdecoder.com/en/glossary/solution-provider/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/solution-provider/"> <p>Leadership role on the delivering side in PM² that bears overall accountability for what the project delivers and names the Project Manager</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/solution-provider/">Solution Provider</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.6</footer> </blockquote>
Found a mistake? Let us know, we check every report.