Continued business justification

Definition

Continued business justification is one of the seven PRINCE2 principles. It requires that there is a valid reason for the project at all times: the expected benefits must justify the costs, effort and risks, and the project must fit the objectives of the commissioning organization. The justification is not checked once at the start and then forgotten; it is kept up to date and reassessed at the end of every stage. If it no longer holds, for example because market conditions, costs or priorities have shifted, the project should be adjusted or closed early. The justification is documented in the business case, which is owned by the Executive.

Equivalents in other frameworks

Concept Economic justification of an initiative · two frameworks reviewed

Equivalents of Continued business justification in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Business casepartially overlappingPrinciple of reviewing the justification throughout the project; the document itself is the business case.
PMI / PMBOKBusiness casepartially overlappingPrinciple of reviewing the justification throughout the project; the document itself is the business case.

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Continued business justification
Topic area
Initiating

Distinction

The business case is the document that records the justification; the principle is the commitment to keep reviewing it. Many organizations assess a project economically only when it is approved. PRINCE2 differs by making that assessment recurrent. Even compulsory projects, such as those needed to meet legal requirements, need a justification under this principle, for instance a comparison of several options for meeting the obligation.

In practice

An insurer is building a new customer portal. At the end of the second stage it emerges that a competitor offers a similar platform as a subscription service that costs a fraction of the remaining development budget. The project manager updates the business case, and the Project Board decides to stop the in-house build and to reuse the requirements already written to select the subscription service.

Frequently asked questions

Has a project that is closed early failed in PRINCE2 terms?

Not necessarily. If the justification has disappeared, an orderly closure is a responsible decision, because continuing would tie up money and people without sufficient return.

When is the business justification reviewed?

Mainly before the project starts, at the end of initiation and at every boundary between management stages, and also whenever an exception affects the basis of the project.

Source and context

Reference
PRINCE2 7, Grundprinzipien
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Continued business justification. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/continued-business-justification/

Short form

Hain, D. (n.d.): Continued business justification. PMDecoder, entry on PRINCE2 7, Grundprinzipien. https://pmdecoder.com/en/glossary/continued-business-justification/ (retrieved 24 November 2026)

BibTeX
@misc{continuedbusinessjustification,
  author  = {Hain, Dennis},
  title   = {Continued business justification},
  note    = {PMDecoder, PRINCE2 7, Grundprinzipien},
  url     = {https://pmdecoder.com/en/glossary/continued-business-justification/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/continued-business-justification/">
  <p>PRINCE2 principle: a project must remain worthwhile throughout its life; if the justification is lost, it is changed or stopped.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/continued-business-justification/">Continued business justification</a>, PMDecoder, PRINCE2 7, Grundprinzipien</footer>
</blockquote>

Found a mistake? Let us know, we check every report.