Early finish date
also: Early finish · abbr. EF
Definition
The early finish date, EF for short, is the sum of the early start date and the duration of the activity. It is determined in the forward pass and passed on to the successors, whose early start depends on it. The early finish of the last activity marks the earliest possible project end.
Equivalents in other frameworks
Concept Earliest possible finish of an activity · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Early finish date | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Early finish date
- Topic area
- Network planning
Distinction
The late finish date states when an activity must be finished at the latest without endangering the project end. If the early finish and the late finish differ, the activity has float. The actual completion is only known as the project progresses and can lie before or after the early finish if the duration changes.
In practice
A translation agency takes on a 400-page manual. The translation can start on 3 March, as soon as the source text has been released, and takes twenty working days; its early finish is therefore at the end of March. Because copy-editing follows immediately and the print date is fixed, the agency points out straight away that the release must not come a single day later. The early finish makes this chain comprehensible to the client.
Frequently asked questions
How is the early finish date calculated?
As early start plus duration. Depending on the counting convention, one day is subtracted so that a one-day activity starts and finishes on the same day.
Why is the early finish of the last activity so important?
It shows the earliest possible project end. If it lies after the agreed date, action is needed.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Early finish date. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/early-finish-date/
Hain, D. (n.d.): Early finish date. PMDecoder. https://pmdecoder.com/en/glossary/early-finish-date/ (retrieved 24 November 2026)
@misc{earlyfinishdate,
author = {Hain, Dennis},
title = {Early finish date},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/early-finish-date/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/early-finish-date/"> <p>Earliest possible point in time at which an activity can be completed if it starts on its early start date</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/early-finish-date/">Early finish date</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.