Crashing

Definition

In crashing, the duration of selected activities is shortened by deploying more staff, overtime, additional shifts, more powerful machines or express deliveries. One starts with the activities that determine the end date and where a day gained costs the least extra, and shortens step by step until the target date is reached or further acceleration becomes uneconomical.

Equivalents in other frameworks

Concept Shortening through additional resources · three frameworks reviewed

Equivalents of Crashing in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKCrashingequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Crashing
Topic area
Scheduling

Distinction

Crashing is a schedule compression technique and works through additional means, fast tracking through a changed sequence. Crashing mainly increases costs, fast tracking mainly increases risk. Accelerating activities that have sufficient float gains nothing for the project end, as long as they do not themselves become the ones that determine the end date.

In practice

During the construction of a motorway bridge, the closure threatens to last longer than permitted, which would trigger high contractual penalties. The site management calculates for each critical activity what one day of acceleration costs. The cheapest option is a second shift in steelwork; an additional crane would be more expensive. With the second shift and accelerated delivery of the precast elements, the site gains nine days and stays well below the threatened penalties.

Frequently asked questions

Where does the term crashing come from?

From English, where it refers to squeezing a schedule together. In German it is the usual technical term; occasionally people speak of acceleration through additional resources.

Can any work be accelerated by adding staff?

No. Work with fixed waiting times, such as drying, or work that requires a lot of familiarization becomes hardly any faster, or not at all, with additional staff.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Crashing. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/crashing/

Short form

Hain, D. (n.d.): Crashing. PMDecoder. https://pmdecoder.com/en/glossary/crashing/ (retrieved 24 November 2026)

BibTeX
@misc{crashing,
  author  = {Hain, Dennis},
  title   = {Crashing},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/crashing/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/crashing/">
  <p>Shortening activity durations on the critical path by adding resources, usually at higher cost</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/crashing/">Crashing</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.