Risk transference
Definition
In PMI terms, risk transference is a response strategy for threats. Ownership of the risk and the burden of its consequences pass to another party that is better able to manage or bear it. Common means are insurance, bonds, guarantees, warranties and contract clauses, such as choosing a fixed-price contract in which the cost risk lies with the contractor. The threat itself does not disappear. The third party usually expects something in return for taking it on, such as a premium or a risk surcharge. PMI's counterpart for opportunities is sharing them.
Equivalents in other frameworks
Concept Shifting the consequences of a risk to a third party · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Risk transfer | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- Broader term
- Risk response
- this term
- Risk transference
- Topic area
- Risks and opportunities
Distinction
The term corresponds to the cross-framework concept of risk transfer. Unlike risk avoidance and risk mitigation, risk transference changes neither probability nor impact, only who bears the consequences. Damage to the project's reputation or schedule often cannot be transferred completely.
In practice
For a special exhibition, a museum has loans shipped from abroad. Damage in transit would be unacceptable for the project. The museum takes out transit insurance and engages a specialist art shipper with contractual liability. The financial burden of any damage thus lies with the insurer and the shipper; the risk of a delayed opening remains with the project.
Frequently asked questions
Does transference eliminate the risk?
No. The risk remains; someone else simply bears the financial or contractual consequences. The project must continue to monitor it.
What are the drawbacks of risk transference?
It has a price, and the third party may fail or dispute its obligation. Moreover, not all consequences can be transferred, for example schedule delays or reputational damage.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Risk transference. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-transference/
Risk transference (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/risk-transference/ (retrieved 24 November 2026)
@misc{risktransference,
title = {Risk transference},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/risk-transference/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/risk-transference/"> <p>Strategy that hands a threat, together with responsibility for its consequences, to another party outside the project.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk-transference/">Risk transference</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.