Contingency plan
also: Contingent response
Definition
A contingency plan is ready before it is needed. It describes what exactly will be done when a particular risk occurs, who acts, what resources are available and how the occurrence is recognized. This trigger, such as a missed date or a measured value, is defined in advance so that there is no need for discussion when the situation arises.
Equivalents in other frameworks
Concept Pre-planned response to an occurring risk · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Contingency plan | closely related | denotes the plan with its triggers, the contingency response the reaction itself |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
All designations of this concept side by side
Comparisons
Classification
- this term
- Contingency plan
- Topic area
- Risks and opportunities
Distinction
Preventive actions take effect before the risk occurs and are intended to prevent it; contingency plans take effect afterwards and are intended to limit the damage. A workaround, by contrast, is an unplanned reaction to a problem for which nothing had been prepared. A fallback plan comes into play if the contingency plan does not work either.
In practice
For the switchover of a supermarket chain's checkout system on a Sunday, there is a contingency plan: if the new system is not working in a branch at six o'clock on Monday morning, the old system, which remains installed in parallel for two more weeks, is switched back on there. The regional IT coordinator is responsible, and the trigger is a failed test purchase. The plan is invoked in two of 80 branches, and all of them open on time.
Frequently asked questions
For which risks are contingency plans prepared?
For risks with a significant impact that cannot be adequately prevented, and for accepted risks where quick action would be needed if they occurred.
What is a trigger?
A signal defined in advance that indicates that a risk is occurring or is imminent and that sets the prepared response in motion.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Contingency plan. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/contingency-plan/
Hain, D. (n.d.): Contingency plan. PMDecoder. https://pmdecoder.com/en/glossary/contingency-plan/ (retrieved 24 November 2026)
@misc{contingencyplan,
author = {Hain, Dennis},
title = {Contingency plan},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/contingency-plan/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/contingency-plan/"> <p>Response planned in advance and triggered when a known risk occurs, in order to limit its consequences</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/contingency-plan/">Contingency plan</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.