Project Brief
Definition
In PRINCE2, the project brief summarizes what is known about a project before its initiation. It is created in the process starting up a project from the project mandate and describes background, objectives, scope and exclusions, constraints and assumptions, the outline business case, the project product description, the intended delivery approach and the composition of the project management team. On this basis, the project board decides whether initiation may begin. During initiation the brief serves as the starting point for the project initiation documentation, which supersedes it.
Equivalents in other frameworks
Concept Formal authorization of a project · seven frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Project mandate | partially overlapping | Preliminary form: basis for the decision on initiation; the project itself is authorized with the project initiation documentation. |
| PMI / PMBOK | Project charter | partially overlapping | Preliminary form: basis for the decision on initiation; the project itself is authorized with the project initiation documentation. |
| PM² | Project Charter | partially overlapping | Preliminary form: basis for the decision on initiation; the project itself is authorized with the project initiation documentation. |
| Six Sigma | Six Sigma project charter | partially overlapping | Preliminary form: basis for the decision on initiation; the project itself is authorized with the project initiation documentation. |
| general | Project outline no entry yet | partially overlapping | preliminary form, usually without formal approval |
| Scrum | — | no counterpart | Scrum does not define a formal authorization of a project |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Project Brief
- Topic area
- Initiating
Distinction
The PMI project charter formally puts a project into effect and gives the project manager authority. The project brief, by contrast, only authorizes entry into initiation; authorization of the project itself only follows with the project initiation documentation. In content it is close to what German-speaking practice calls an outline of the assignment (Auftragsskizze).
In practice
For setting up a customer service chat at a municipal utility, the project manager prepares a project brief over three weeks. It describes the objective of relieving the telephone hotline, excludes social media channels, roughly estimates costs and savings and names the project board. The board authorizes initiation with a budget for six weeks of detailed planning.
Frequently asked questions
How detailed does a project brief need to be?
Detailed enough for the project board to make a sound decision on initiation. For small projects, a few pages are often sufficient.
Is the project brief maintained afterwards?
Usually not. Its content passes into the project initiation documentation, which then serves as the valid basis.
Source and context
- Reference
- PRINCE2 7, Managementprodukte
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Project Brief. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-brief/
Hain, D. (n.d.): Project Brief. PMDecoder, entry on PRINCE2 7, Managementprodukte. https://pmdecoder.com/en/glossary/project-brief/ (retrieved 24 November 2026)
@misc{projectbrief,
author = {Hain, Dennis},
title = {Project Brief},
note = {PMDecoder, PRINCE2 7, Managementprodukte},
url = {https://pmdecoder.com/en/glossary/project-brief/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/project-brief/"> <p>PRINCE2 management product describing a planned project in enough detail for the project board to decide whether initiation may begin.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-brief/">Project Brief</a>, PMDecoder, PRINCE2 7, Managementprodukte</footer> </blockquote>
Found a mistake? Let us know, we check every report.