Risk management plan

Definition

In PMI terms, the risk management plan is a component of the project management plan. It does not describe individual risks but the approach: which methods and data sources are used, who has which role, what budget and time are set aside for risk work and how often it takes place. It often also contains the risk categories or a risk breakdown structure, the risk appetite of key stakeholders, definitions of probability and impact levels, a probability and impact matrix, and requirements for reporting and tracking. Its scope and level of detail depend on the size and significance of the project.

Equivalents in other frameworks

Concept Arrangements for risk management in a project · four frameworks reviewed

Equivalents of Risk management plan in other frameworks
FrameworkTerm thereRelationNote
generalRisk management planequivalent—
PRINCE2Risk Management Approachclosely relatedSame purpose; additionally translates the organization’s risk appetite into tolerances for the project board.
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Risk management plan

Distinction

The term corresponds to the cross-framework concept of the risk management plan. The risk register documents the specific risks and responses; the risk management plan sets out the rules for working with them. A contingency plan, by contrast, is the prepared response to a single risk.

In practice

For a project introducing a patient portal, the risk management plan specifies risk workshops at the start of each phase, a five-point scale for probability and impact, a colour-coded matrix, a risk coordinator in the project management office and a monthly report to the steering committee.

Frequently asked questions

When is the risk management plan created?

Early in planning, before risks are systematically recorded, because it sets the standards for that work. It is updated when significant changes occur.

Does a small project need its own risk management plan?

It can be very brief or refer to an organizational template. What matters is that the rules for handling risks are known and agreed.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Risk management plan. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-management-plan-pmi/

Short form

Risk management plan (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/risk-management-plan-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{riskmanagementplanpmi,
  title   = {Risk management plan},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/risk-management-plan-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/risk-management-plan-pmi/">
  <p>Subsidiary plan setting the methods, roles, budget, rating scales and reporting for risk work on the project, not the risks themselves.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk-management-plan-pmi/">Risk management plan</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.