S-curve
Definition
The S-curve plots cumulative values against time, such as planned costs, hours used or work performed. Its typical shape arises because projects start slowly, consume most resources in the middle and fewer again towards the end. If the planned and actual curves are superimposed, the gap between them shows at a glance whether the project is ahead of or behind plan.
Equivalents in other frameworks
Concept Cumulative development over the project duration · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | S-curve analysis | closely related | denotes the analysis based on the curve, not the curve itself |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
All designations of this concept side by side
Comparisons
Classification
- this term
- S-curve
- Topic area
- Monitoring and control
Distinction
A resource histogram shows the demand per unit of time as columns; the S-curve shows its cumulative total over time. Earned value management combines three such curves: planned value, actual cost and earned value. The project S-curve shares only its shape with the S-curve of technology development, which describes leaps in the performance of new technologies.
In practice
A client has the S-curve of construction costs presented every month. After eight months, the actual curve is well below the planned curve, which at first looks like a saving. Comparison with the performance curve, however, shows that simply less has been built than planned: the project is not cheaper but slower. The project controllers then clarify the staffing level of the shell construction contractor.
Frequently asked questions
Why is the curve S-shaped?
Because the start-up and close-out phases work with few staff and little material, while the main phase consumes the most.
What does a flatter actual curve indicate?
On its own, little. Only comparison with the work performed shows whether less has been spent or less has been achieved.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). S-curve. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/s-curve/
Hain, D. (n.d.): S-curve. PMDecoder. https://pmdecoder.com/en/glossary/s-curve/ (retrieved 24 November 2026)
@misc{scurve,
author = {Hain, Dennis},
title = {S-curve},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/s-curve/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/s-curve/"> <p>Chart of a project's cumulative costs, labour hours or performance over time, usually shaped like an elongated S</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/s-curve/">S-curve</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.