Phase gate

Definition

In PMI usage, a phase gate is a review held when a project or programme phase ends. An authorized body decides whether the undertaking moves on to the next phase, continues with changes or ends. The decision is based on the results of the completed phase, the current status of objectives, cost, schedule and risks, and whether the justification for the undertaking still holds. Phase gates are especially common in predictive life cycles in which phases follow one another. They link project work to the governance of the organization.

Equivalents in other frameworks

Concept Decision point between project phases · six frameworks reviewed

Equivalents of Phase gate in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Gateequivalent—
PM²Phase Gateequivalent—
Six SigmaTollgateclosely relatedbetween the phases of the DMAIC cycle
PRINCE2Managing a stage boundarypartially overlappingThe Project Manager’s preparation of the decision point; the decision itself is taken by the Project Board.
Scrum—no counterpartcontinuation is decided continuously in the Sprint Review
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Phase gate

Distinction

The ISO 21506 gate and the PM² phase gate are equivalent; the Six Sigma tollgate is closely related but refers to the phases of the improvement cycle. A milestone marks a significant event but does not necessarily require a decision about continuation. A quality review assesses results without deciding on the undertaking as a whole. The phase gate is also known as a phase review, stage gate or kill point.

In practice

A pharmaceutical company develops a new diagnostic device in four phases. At the end of the concept phase, the project team presents the prototype, the revised cost estimate and the market analysis to the development board. Because the manufacturing cost is well above target, the board releases the next phase only on condition that a cheaper sensor concept is examined. The decision and the condition are recorded in the minutes of the phase gate.

Frequently asked questions

Who decides at a phase gate?

A body with decision-making authority over the undertaking, such as the sponsor, a steering committee or a portfolio board. The project manager prepares the documents and makes a recommendation but does not decide.

Are there phase gates in agile undertakings?

Rarely in pure form, because delivery and adjustment happen continuously. In hybrid approaches, however, gates remain common, for example before series production or before a major investment decision.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Phase gate. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/phase-gate-pmi/

Short form

Phase gate (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/phase-gate-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{phasegatepmi,
  title   = {Phase gate},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/phase-gate-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/phase-gate-pmi/">
  <p>Formal decision point between two phases at which an authorized body uses the phase results to decide how the undertaking proceeds.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/phase-gate-pmi/">Phase gate</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.