Work breakdown structure dictionary
Definition
The work breakdown structure dictionary adds to the tree structure everything that does not fit into a box. For every element it contains the identifier, a description of the content and expected results, boundaries, the responsible unit, dependencies and, where needed, budget, dates and acceptance criteria. This way everyone involved understands an element in the same way, even if they did not take part in planning it.
Equivalents in other frameworks
Concept Description of work breakdown structure elements · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | WBS dictionary | equivalent | — |
| PRINCE2 | Product Description | partially overlapping | Describes products rather than work and defines quality criteria, checking methods and responsibilities. |
| general | Work package description | partially overlapping | describes a single work package, not all elements of the work breakdown structure |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Work breakdown structure dictionary
- Topic area
- Planning and project structure
Distinction
A work package description sets out a single work package in detail. The dictionary covers all elements of the work breakdown structure, including the parent elements, and can contain work package descriptions or refer to them. The work breakdown structure itself shows the hierarchy, the dictionary the content.
In practice
For a satellite ground segment, the work breakdown structure comprises 180 elements. Under "3.2.4 Antenna control, software", the dictionary states that the element covers the control software including tests, but not the hardware interface, which is listed under 3.2.3. When a new team member wants to book effort for the interface to 3.2.4, a look at the dictionary settles the assignment before costs are booked incorrectly.
Frequently asked questions
How detailed does the dictionary have to be?
Detailed enough for the content and boundaries of each element to be unambiguous. A few sentences are often enough for parent elements; work packages need more.
Who maintains the dictionary?
The project manager or the project office, with input from the people responsible for the individual elements. Changes to the work breakdown structure are reflected in the dictionary.
Source and context
- Reference
- ISO 21506:2024, 3.97
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Work breakdown structure dictionary. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/work-breakdown-structure-dictionary/
Hain, D. (n.d.): Work breakdown structure dictionary. PMDecoder, entry on ISO 21506:2024, 3.97. https://pmdecoder.com/en/glossary/work-breakdown-structure-dictionary/ (retrieved 24 November 2026)
@misc{workbreakdownstructuredictionary,
author = {Hain, Dennis},
title = {Work breakdown structure dictionary},
note = {PMDecoder, ISO 21506:2024, 3.97},
url = {https://pmdecoder.com/en/glossary/work-breakdown-structure-dictionary/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/work-breakdown-structure-dictionary/"> <p>Companion document to the work breakdown structure that records, element by element, content, results, responsibility and other details.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/work-breakdown-structure-dictionary/">Work breakdown structure dictionary</a>, PMDecoder, ISO 21506:2024, 3.97</footer> </blockquote>
Found a mistake? Let us know, we check every report.