Critical path

Definition

The critical path is the chain of activities with the longest total duration from the start to the end of the project. It therefore determines the shortest duration the project can achieve with the given logic. Any delay to an activity on this path moves the project end date unless action is taken. In a schedule without imposed dates, activities on the critical path usually have zero total float. A project can have several critical paths, and the critical path can change over time as activities progress faster or slower than planned.

Equivalents in other frameworks

Concept Longest sequence of activities without float · three frameworks reviewed

Equivalents of Critical path in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Critical pathequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Critical path

Distinction

The term corresponds to the critical path as used in ISO 21506 and German network planning (kritischer Pfad). The critical path method is the calculation technique; the critical path is its result. It differs from the critical chain of the critical chain method in that resource constraints are not taken into account. Near-critical paths are paths with little float that can easily become critical.

In practice

When a school is refurbished, the schedule calculation shows that asbestos removal, screed work, drying and floor coverings form the critical path. When drying takes a week longer because of humidity, the reopening date moves back accordingly. The painting work, on the other hand, is not on the path; moving it by three days does not change the end date.

Frequently asked questions

Can an activity on the critical path have float?

Not in the pure calculation. If fixed dates are imposed, however, the path with the least float may show a positive or negative value. The critical path is then the one with the smallest total float.

How often should the critical path be reviewed?

At every schedule update. Even small deviations on other paths can cause a previously non-critical path to become the longest.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Critical path. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/critical-path-pmi/

Short form

Critical path (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/critical-path-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{criticalpathpmi,
  title   = {Critical path},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/critical-path-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/critical-path-pmi/">
  <p>The chain of activities that takes longest from start to finish and therefore fixes the minimum time the project can take.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/critical-path-pmi/">Critical path</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.