Product breakdown structure

abbr. PBS

Definition

The product breakdown structure divides the overall result of a project into sub-products, such as a building into shell, envelope, building services and external works, or a software system into modules and documents. It describes what should exist at the end, not the activities needed to get there. Deliverables, quality criteria and the work breakdown structure can be derived from it. PRINCE2 explicitly uses this view as the basis for product-based planning.

Equivalents in other frameworks

Concept Hierarchical decomposition of project scope · three frameworks reviewed

Equivalents of Product breakdown structure in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKWork breakdown structurepartially overlappingbreaks down the result into sub-products instead of the work into work packages
PRINCE2Product Breakdown Structurepartially overlappingBreakdown into products rather than work; corresponds to the product breakdown structure under ISO 21506.
ScrumProduct Backlogpartially overlappingalso decomposes the scope, but ordered by value rather than hierarchically

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Product breakdown structure

Distinction

The work breakdown structure breaks down the work, the product breakdown structure the result; the two can be closely related. A bill of materials lists the parts of a series product with quantities for manufacturing and purchasing, whereas the product breakdown structure is used to plan a one-off project result and also includes documents and services.

In practice

For a new employee app, the project team breaks the result down into the app for two operating systems, an administration interface, an interface to the HR software, a data protection concept, training materials and an operations manual. While drawing it up, the team notices that nobody had thought of the operations manual. Only then is the work breakdown structure created, with the work packages that lead to these sub-products.

Frequently asked questions

Do you need both a product and a work breakdown structure?

For manageable projects, a results-oriented work breakdown structure is often enough. For complex results, the product breakdown structure helps to ensure that nothing is forgotten.

What is product-based planning?

A planning approach that first describes the results and then derives the activities and their sequence from them. It prevents work from being planned that does not contribute to any required result.

Source and context

Reference
ISO 21506:2024, 3.53
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Product breakdown structure. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/product-breakdown-structure/

Short form

Hain, D. (n.d.): Product breakdown structure. PMDecoder, entry on ISO 21506:2024, 3.53. https://pmdecoder.com/en/glossary/product-breakdown-structure/ (retrieved 24 November 2026)

BibTeX
@misc{productbreakdownstructure,
  author  = {Hain, Dennis},
  title   = {Product breakdown structure},
  note    = {PMDecoder, ISO 21506:2024, 3.53},
  url     = {https://pmdecoder.com/en/glossary/product-breakdown-structure/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/product-breakdown-structure/">
  <p>Hierarchical breakdown of a project's result into its sub-products and components.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/product-breakdown-structure/">Product breakdown structure</a>, PMDecoder, ISO 21506:2024, 3.53</footer>
</blockquote>

Found a mistake? Let us know, we check every report.