Portfolio management
Definition
Portfolio management decides which undertakings an organization starts, continues, puts on hold or stops. It is based on strategic objectives, available budgets and capacity, and the benefits and risks of the individual undertakings. Unlike project and programme management, it does not ask how an undertaking can be carried out well, but whether it is the right undertaking.
Equivalents in other frameworks
Concept Selecting and steering an organization's initiatives · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Portfolio management | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Portfolio management
- Topic area
- Portfolios and programmes
Distinction
The portfolio is the set of undertakings, portfolio management the activity of steering them. Programme management coordinates projects that are related in content, while portfolio management also considers undertakings that are independent of each other. It differs from multi-project management, which mainly balances resources between running projects, by its strategic selection step.
In practice
A software company collects all project proposals twice a year. Each proposal receives a short assessment of its strategic contribution, expected benefit, effort and risk. A board made up of management and division heads selects what fits into the available capacity. Running projects whose benefit assumptions no longer hold are explicitly up for discussion rather than continuing out of habit.
Frequently asked questions
What criteria does portfolio management use?
Typically strategic fit, economic benefit, urgency, risk, resource requirements and dependencies on other undertakings.
How often should a portfolio be reviewed?
At least once a year, quarterly in dynamic markets. What matters is that the review leads to real decisions.
Source and context
- Reference
- ISO 21506:2024, 3.48
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Portfolio management. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/portfolio-management/
Hain, D. (n.d.): Portfolio management. PMDecoder, entry on ISO 21506:2024, 3.48. https://pmdecoder.com/en/glossary/portfolio-management/ (retrieved 24 November 2026)
@misc{portfoliomanagement,
author = {Hain, Dennis},
title = {Portfolio management},
note = {PMDecoder, ISO 21506:2024, 3.48},
url = {https://pmdecoder.com/en/glossary/portfolio-management/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/portfolio-management/"> <p>Selection, prioritization and ongoing control of all of an organization's projects and programmes with a view to its strategy.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/portfolio-management/">Portfolio management</a>, PMDecoder, ISO 21506:2024, 3.48</footer> </blockquote>
Found a mistake? Let us know, we check every report.