Risk register

Definition

In PMI terms, the risk register is the central record of individual project risks. It holds the results of risk work: identifier and description of each risk, cause, owner, rating by probability and impact, priority, chosen response strategy, agreed actions, triggers, reserves and status. It is created during the first risk identification and kept up to date throughout the project. PMI counts it among the project documents. For an overall view of project uncertainty, PMI also provides for a risk report that summarizes the register.

Equivalents in other frameworks

Concept Central list of project risks · four frameworks reviewed

Equivalents of Risk register in other frameworks
FrameworkTerm thereRelationNote
PRINCE2Risk RegisterequivalentThe PRINCE2 register explicitly includes opportunities as well.
generalRisk registerequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Risk register

Distinction

The term corresponds to the cross-framework concept of the risk register. The issue log records problems that have occurred; the risk register records future uncertainties. The risk management plan specifies how the register is kept but does not itself contain individual risks.

In practice

The team building a new bridge keeps the risk register as a shared spreadsheet. Each row contains a risk with owner, rating and actions. After a flood causes work to stop, the risk “water level above site dewatering capacity” is rated higher, an additional sheet pile wall is added as an action and the status is set to “in progress”.

Frequently asked questions

Are closed risks deleted from the risk register?

It is usual to mark them as closed rather than delete them. This keeps a record of how the project handled them and keeps the data available for lessons learned.

Who maintains the risk register?

The project manager ensures that it is kept. The owners of individual risks provide updates to their entries.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Risk register. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-register-pmi/

Short form

Risk register (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/risk-register-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{riskregisterpmi,
  title   = {Risk register},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/risk-register-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/risk-register-pmi/">
  <p>Record in which the findings of risk management on individual risks are captured and continually updated.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk-register-pmi/">Risk register</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.