Activity-on-node network
abbr. AON, PDM
Definition
In an activity-on-node network, each activity is a box that usually contains its number, name, duration, earliest and latest dates and float. Arrows between the boxes show the logical relationships. This representation allows all four types of relationship as well as time intervals between activities, and it is the form commonly used in scheduling software today.
Equivalents in other frameworks
Concept Network diagram with activities on nodes · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Precedence diagramming method | closely related | names the diagramming method, the activity-on-node network diagram its result |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Activity-on-node network
- Topic area
- Network planning
Distinction
In an activity-on-arrow network, the activities lie on the arrows, only finish-to-start relationships can be shown directly, and dummy activities are often needed. In an event-on-node network, the focus is on events and the activities recede into the background. Internationally, the activity-on-node network is widely known as the precedence diagramming method.
In practice
An engineering consultancy first trains new staff in scheduling on paper: each person draws twelve activity nodes with durations and arrows for a new garage. Each node has fields for the earliest and latest dates, which are calculated by hand. Anyone who has done this once later understands why the software suddenly shows a different critical path after a duration has been changed.
Frequently asked questions
What does an activity node contain?
At least its number, name and duration. It usually also has four date fields for early start, early finish, late start and late finish, as well as figures for total float and free float.
Why has the activity-on-node network become the standard?
Because it needs no dummy activities, allows all types of links and is easy to implement in software.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Activity-on-node network. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/activity-on-node-network/
Hain, D. (n.d.): Activity-on-node network. PMDecoder. https://pmdecoder.com/en/glossary/activity-on-node-network/ (retrieved 24 November 2026)
@misc{activityonnodenetwork,
author = {Hain, Dennis},
title = {Activity-on-node network},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/activity-on-node-network/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/activity-on-node-network/"> <p>Form of network schedule in which activities are shown as nodes and their dependencies as connecting arrows</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/activity-on-node-network/">Activity-on-node network</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.