Opportunity

Definition

An opportunity is the positive side of uncertainty. It exists when something could happen that would allow a project to finish faster, more cheaply, better or with greater benefit, such as falling material prices, an early permit or a new technique that saves work. Opportunities are identified, assessed and given responses in the same way as threats, so that they are actually exploited.

Equivalents in other frameworks

Concept Risk with a positive effect on project objectives · three frameworks reviewed

Equivalents of Opportunity in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKOpportunityequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Opportunity

Distinction

ISO 21506 treats opportunities and threats alike as risks, whereas in everyday language risk usually means only the negative side. The threat is the counterpart of the opportunity. In a SWOT analysis, opportunities are external possibilities, while strengths are internal characteristics.

In practice

While planning a new administrative building, the project team learns that a funding programme for timber construction is about to be launched. The opportunity is entered in the register: medium probability, potential grant of up to ten per cent. As a response, the team has a timber structural design checked in parallel so that an application can be submitted immediately. When the programme starts, the client submits the application in the first week.

Frequently asked questions

How are opportunities handled?

With strategies that mirror those for threats: making them happen deliberately, enhancing them, sharing them with partners or consciously waiting.

Why are opportunities often overlooked?

Because risk workshops usually ask about dangers. A separate question about possible improvements helps to capture opportunities systematically.

Source and context

Reference
ISO 21506:2024, 3.39
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Opportunity. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/opportunity/

Short form

Hain, D. (n.d.): Opportunity. PMDecoder, entry on ISO 21506:2024, 3.39. https://pmdecoder.com/en/glossary/opportunity/ (retrieved 24 November 2026)

BibTeX
@misc{opportunity,
  author  = {Hain, Dennis},
  title   = {Opportunity},
  note    = {PMDecoder, ISO 21506:2024, 3.39},
  url     = {https://pmdecoder.com/en/glossary/opportunity/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/opportunity/">
  <p>Uncertain event or circumstance that, if it occurs, would have a positive effect on a project's objectives.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/opportunity/">Opportunity</a>, PMDecoder, ISO 21506:2024, 3.39</footer>
</blockquote>

Found a mistake? Let us know, we check every report.