Stakeholder
Definition
Stakeholders are all those for whom an undertaking matters or who matter to the undertaking. They include the client, the project team and future users as well as suppliers, authorities, local residents or associations. ISO 21506 deliberately draws the circle wide: it covers not only those actually affected but also those who merely feel affected, and it applies to projects, programmes and portfolios alike. In practice, this perceived impact is often what triggers resistance.
Equivalents in other frameworks
Concept Parties involved in or affected by an initiative · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Stakeholder | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Stakeholder
- Topic area
- Stakeholders and communication
Distinction
The project team is part of the stakeholders, not their opposite. Stakeholder analysis identifies who belongs to this group and how influence and interests are distributed; stakeholder management derives from this how each group is dealt with. The client is a particularly important stakeholder, but not the only one.
In practice
A municipality is planning a cycle superhighway through a residential area. The stakeholder analysis initially lists the administration, the planning firm, the cycling association and landowners. At the first public information event, parents from a primary school come forward, worried about their children's safety, even though the route does not touch the school. The project manager adds the group as a stakeholder, invites them to a site visit and has the crossing at the main road made safer as well.
Frequently asked questions
Are stakeholders only people outside the project?
No. Stakeholders also include the project team, the sponsor and future users, as well as suppliers, authorities or local residents. What matters is whether someone can influence the project or is affected by it.
How do you keep track of many stakeholders?
With a stakeholder analysis: it records who is involved or affected, how much influence and interest they have and what their attitude towards the project is. From this you decide whom to involve closely, whom to inform regularly and whom merely to monitor.
Are there other words for stakeholder?
Common alternatives are interested parties or project participants. Neither covers the term fully: participants suggests active involvement, whereas stakeholders also include people who are affected but do not work on the project.
Source and context
- Reference
- ISO 21506:2024, 3.86
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Stakeholder. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/stakeholder/
Hain, D. (n.d.): Stakeholder. PMDecoder, entry on ISO 21506:2024, 3.86. https://pmdecoder.com/en/glossary/stakeholder/ (retrieved 24 November 2026)
@misc{stakeholder,
author = {Hain, Dennis},
title = {Stakeholder},
note = {PMDecoder, ISO 21506:2024, 3.86},
url = {https://pmdecoder.com/en/glossary/stakeholder/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/stakeholder/"> <p>Anyone with an interest in an undertaking such as a project, who can influence it or considers themselves affected by it, whether person, group or organization.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/stakeholder/">Stakeholder</a>, PMDecoder, ISO 21506:2024, 3.86</footer> </blockquote>
Found a mistake? Let us know, we check every report.