Managing a stage boundary
Definition
Managing a stage boundary provides the PRINCE2 Project Board with the basis for deciding whether the project should continue. Towards the end of a management stage, the project manager assesses the results, plans the next stage in detail, updates the project plan and the business case, and reports on the stage just completed. The same process is used after an exception to prepare an exception plan that replaces the current plan. The decision itself is taken by the Project Board in the process directing a project.
Equivalents in other frameworks
Concept Decision point between project phases · six frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Gate | partially overlapping | The Project Manager’s preparation of the decision point; the decision itself is taken by the Project Board. |
| PMI / PMBOK | Phase gate | partially overlapping | The Project Manager’s preparation of the decision point; the decision itself is taken by the Project Board. |
| PM² | Phase Gate | partially overlapping | The Project Manager’s preparation of the decision point; the decision itself is taken by the Project Board. |
| Six Sigma | Tollgate | partially overlapping | The Project Manager’s preparation of the decision point; the decision itself is taken by the Project Board. |
| Scrum | — | no counterpart | continuation is decided continuously in the Sprint Review |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Managing a stage boundary
- Topic area
- Monitoring and control
Distinction
Gate, phase gate and phase transition denote the decision point itself. Managing a stage boundary is the project manager’s preparation for that point, including planning and updating the justification. In PRINCE2, preparation and decision therefore fall into two processes and two levels.
In practice
At the end of the pilot stage of a telemedicine project, the project manager evaluates feedback from the participating practices. He plans the roll-out stage with training and a helpline, recalculates the benefits and submits a report to the Project Board. The Project Board authorizes the next stage with a slightly increased budget.
Frequently asked questions
Who decides at the stage boundary?
The Project Board. The project manager prepares the decision and submits the documents, but the authorization belongs to the process directing a project.
Can a project be closed at a stage boundary?
Yes. If the assessment shows that the justification no longer holds, the Project Board can order premature closure instead of authorizing the next stage.
Source and context
- Reference
- PRINCE2 7, Prozesse
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Managing a stage boundary. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/managing-a-stage-boundary/
Hain, D. (n.d.): Managing a stage boundary. PMDecoder, entry on PRINCE2 7, Prozesse. https://pmdecoder.com/en/glossary/managing-a-stage-boundary/ (retrieved 24 November 2026)
@misc{managingastageboundary,
author = {Hain, Dennis},
title = {Managing a stage boundary},
note = {PMDecoder, PRINCE2 7, Prozesse},
url = {https://pmdecoder.com/en/glossary/managing-a-stage-boundary/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/managing-a-stage-boundary/"> <p>PRINCE2 process at the end of a stage: assessing results, planning the next stage, updating the business case and preparing authorization.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/managing-a-stage-boundary/">Managing a stage boundary</a>, PMDecoder, PRINCE2 7, Prozesse</footer> </blockquote>
Found a mistake? Let us know, we check every report.