Actual cost
also: Actual cost of work performed · abbr. AC, ACWP
Definition
Actual cost comprises all costs that have really arisen for a project or a work package up to a given point in time: booked working hours, materials, subcontracted services, travel and, depending on the rules applied, overheads. For meaningful control, these costs are recorded using the same structure as the budget, usually by work package, and accrued to the same cut-off date at which progress is measured.
Equivalents in other frameworks
Concept Actual cost of work performed · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Actual cost | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Actual cost
- Topic area
- Monitoring and control
Distinction
Actual cost is not the same as payments: work can be done but not yet paid for, and an advance payment can be made before the corresponding work has been delivered. Planned costs describe what a piece of work should cost, actual cost what it did cost. In earned value management, comparing earned value with actual cost gives the cost variance.
In practice
On a construction project, the accounts show costs of 1.1 million euros at the end of March. The project manager knows, however, that the structural contractor will only invoice its March work in April and that a delivery of windows has already been installed but not yet invoiced. After accruing both items, actual cost comes to 1.35 million euros. Only this figure allows a meaningful comparison with progress.
Frequently asked questions
Why do actual cost and the accounts often differ?
Because invoices arrive with a delay and work is booked at different times from when it was done. Accruals are therefore made for project control.
Do internal staff costs count as actual cost?
Yes, if the project is responsible for them. They are usually determined from booked hours and agreed internal charge rates.
Source and context
- Reference
- ISO 21506:2024, 3.3
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Actual cost. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/actual-cost/
Hain, D. (n.d.): Actual cost. PMDecoder, entry on ISO 21506:2024, 3.3. https://pmdecoder.com/en/glossary/actual-cost/ (retrieved 24 November 2026)
@misc{actualcost,
author = {Hain, Dennis},
title = {Actual cost},
note = {PMDecoder, ISO 21506:2024, 3.3},
url = {https://pmdecoder.com/en/glossary/actual-cost/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/actual-cost/"> <p>Costs actually incurred for the project work carried out up to a cut-off date.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/actual-cost/">Actual cost</a>, PMDecoder, ISO 21506:2024, 3.3</footer> </blockquote>
Found a mistake? Let us know, we check every report.