Project assurance
Definition
Project assurance gives the commissioning organization a reliable view of the state of a project that does not rest solely on the project manager's reports. It includes, for example, planned reviews at phase transitions, spot checks of plans and results, interviews with the team and checks on whether the business case, risks and quality are still sound. The activities are defined in advance and carried out systematically. The same principle applies to programmes.
Equivalents in other frameworks
Concept Independent assurance of a project for its directing level · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | Project Assurance (PRINCE2) | closely related | In PRINCE2 split into business, user and supplier perspectives and a responsibility of the board members. |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Project assurance
- Topic area
- Quality
Distinction
Quality assurance builds confidence that requirements for processes and results are being met; project assurance builds confidence that the project as a whole will achieve its objectives. Risk assurance focuses on risks and on whether the investment is sound. In PRINCE2, project assurance is a responsibility of the project board that must remain independent of the project manager.
In practice
A federal agency has every IT project worth more than two million euros accompanied by a dedicated project assurance unit. Before each release of the next phase, the unit carries out a one-day review and gives the sponsor a three-level rating. On a project to modernize a register, it finds that the tests are reported as green but cover only a third of the interfaces. The sponsor releases the next phase only after this has been remedied.
Frequently asked questions
Who carries out project assurance?
People who are independent of the project manager, such as representatives of the sponsor, a project management office or external reviewers. They report to the sponsor or steering committee, not to the project manager.
Is project assurance a sign of mistrust?
No. It also protects the project manager, because problems become visible early and objectively. What matters is that findings are discussed openly and not used to assign blame.
Source and context
- Reference
- ISO 21506:2024, 3.62
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Project assurance. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-assurance/
Hain, D. (n.d.): Project assurance. PMDecoder, entry on ISO 21506:2024, 3.62. https://pmdecoder.com/en/glossary/project-assurance/ (retrieved 24 November 2026)
@misc{projectassurance,
author = {Hain, Dennis},
title = {Project assurance},
note = {PMDecoder, ISO 21506:2024, 3.62},
url = {https://pmdecoder.com/en/glossary/project-assurance/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/project-assurance/"> <p>Independent, planned review of a project that gives the sponsor and the commissioning organization a reliable view of whether it is on course.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-assurance/">Project assurance</a>, PMDecoder, ISO 21506:2024, 3.62</footer> </blockquote>
Found a mistake? Let us know, we check every report.