Analogous estimating

also: Analogy-based estimating, Top-down estimating

Definition

In analogous estimating, a new undertaking is compared with a similar one that has already been completed. Its actual values serve as the starting point and are adjusted for size, difficulty or conditions. The technique is quick and needs little detailed knowledge of the new project. It is therefore particularly suitable for early phases, but it is only as good as the comparability of the projects.

Equivalents in other frameworks

Concept Estimating from comparable initiatives · one framework reviewed

Equivalents of Analogous estimating in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKAnalogous estimatingequivalent—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

Broader term
Effort estimation
this term
Analogous estimating

Distinction

Parametric estimating calculates with a relationship between metrics, such as cost per square metre; analogous estimating compares whole projects or larger parts of them. Bottom-up estimating builds the overall estimate from many individual estimates and is more accurate, but takes more effort. Often one starts with an analogy and refines the estimate from the bottom up later.

In practice

An energy utility is planning the renewal of a substation. Two years ago it modernized an almost identical substation, which took 14 months and cost 6.2 million euros. For the new project, the planners initially use the same values, increase the costs by the material prices that have risen in the meantime and the duration by two months, because the site is harder to access. The estimate serves as the basis for budget approval.

Frequently asked questions

When is an analogous estimate reliable?

When the reference project really is similar, its actual values were recorded correctly and the differences are deliberately taken into account.

What are typical mistakes?

Reference projects are adopted uncritically, price increases and learning effects are forgotten, or people remember planned values rather than actual ones.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Analogous estimating. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/analogous-estimating/

Short form

Hain, D. (n.d.): Analogous estimating. PMDecoder. https://pmdecoder.com/en/glossary/analogous-estimating/ (retrieved 24 November 2026)

BibTeX
@misc{analogousestimating,
  author  = {Hain, Dennis},
  title   = {Analogous estimating},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/analogous-estimating/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/analogous-estimating/">
  <p>Estimating technique that derives effort, duration or cost from the actual values of a comparable earlier project</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/analogous-estimating/">Analogous estimating</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.