Secondary risk
Definition
In PMI terms, a secondary risk is a risk that arises only because a risk response is implemented. Every action changes the project: it ties up staff, shifts dates, or brings in new partners or technologies. Uncertainties of their own can follow from this. PMI recommends asking specifically about such follow-on risks when planning responses, recording them in the risk register, and assessing and treating them like other risks. A response only makes sense if the new risks weigh less overall than the original one.
Equivalents in other frameworks
Concept Risk arising from a response · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Secondary risk | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- Broader term
- Risk
- this term
- Secondary risk
- Topic area
- Risks and opportunities
Distinction
The term corresponds to the cross-framework concept of secondary risk. A residual risk is the part of the original risk that remains after the response; a secondary risk is a different, new risk. Residual risk in ISO 21506 corresponds to PMI's residual risk, not to secondary risk.
In practice
To mitigate schedule delays caused by an unreliable supplier, a mechanical engineering project engages a second supplier. Its components come from a different plant and could have slightly different dimensions. The team records this as a secondary risk and plans an additional incoming inspection.
Frequently asked questions
Does every secondary risk need a response of its own?
It is assessed like any other risk. If it lies above the thresholds it needs its own response; otherwise it can be accepted and monitored.
Why is identifying secondary risks important?
Without this view, a well-intended action can leave the project worse off overall. The assessment shows whether the response pays off on balance.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Secondary risk. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/secondary-risk-pmi/
Secondary risk (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/secondary-risk-pmi/ (retrieved 24 November 2026)
@misc{secondaryriskpmi,
title = {Secondary risk},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/secondary-risk-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/secondary-risk-pmi/"> <p>Follow-on risk that arises only because a risk response is carried out and must be assessed and handled like any other risk.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/secondary-risk-pmi/">Secondary risk</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.