Lessons Report

Definition

In PRINCE2 the Lessons Report is the report through which a project makes its experience usable beyond itself. It summarizes the main entries of the Lessons Log, puts them in context and derives recommendations, for example for the organization’s standards, templates, estimating data or training. Typical occasions are the end of a management stage and project closure, but it can be produced at any time if a lesson should be passed on immediately. The Project Manager prepares it; the Project Board reviews it and decides to whom it is forwarded. Its content covers what went well and what went badly, the causes that can be identified, where useful measurements of effort and quality, and concrete proposals.

Equivalents in other frameworks

Concept Captured lessons from projects · four frameworks reviewed

Equivalents of Lessons Report in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Lessons learnedclosely relatedReport that evaluates selected lessons and passes them on to the organization.
PMI / PMBOKLessons learnedclosely relatedReport that evaluates selected lessons and passes them on to the organization.
PM²Project-End Reportpartially overlappingcontains lessons learned, but also reports on the performance and outcome of the project
ScrumSprint Retrospectivepartially overlappingcontinually improves the way the team works instead of documenting lessons for other initiatives

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Lessons Report
Topic area
Closing

Distinction

The Lessons Log collects experience continuously; the Lessons Report is the selected, evaluated version for recipients outside the project. The End Project Report evaluates the project’s overall performance and can refer to the Lessons Report. The PM² Project-End Report combines both purposes in one document. Lessons learned are the insights themselves; the Lessons Report is the vehicle that carries them.

In practice

After the first stage of a project introducing electronic case files, the project manager notes that the data protection review of each new module took three weeks because it only started after completion. She writes a short Lessons Report recommending that the data protection officer be involved at the design stage. The Project Board forwards it to the project office, which adds the recommendation to the template for project plans.

Frequently asked questions

Does a Lessons Report have to wait until the project ends?

No. It is often produced at the end of a stage or the project, but can be written at any time if a lesson is urgent for other undertakings.

Who receives the Lessons Report?

The Project Board reviews it and decides on distribution, for example to a project office, to the quality management function or to projects running in parallel.

Source and context

Reference
PRINCE2 7, Managementprodukte
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Lessons Report. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/lessons-report/

Short form

Hain, D. (n.d.): Lessons Report. PMDecoder, entry on PRINCE2 7, Managementprodukte. https://pmdecoder.com/en/glossary/lessons-report/ (retrieved 24 November 2026)

BibTeX
@misc{lessonsreport,
  author  = {Hain, Dennis},
  title   = {Lessons Report},
  note    = {PMDecoder, PRINCE2 7, Managementprodukte},
  url     = {https://pmdecoder.com/en/glossary/lessons-report/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/lessons-report/">
  <p>PRINCE2 report that evaluates a project’s experience and passes it to the organization or other undertakings, usually at stage or project end.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/lessons-report/">Lessons Report</a>, PMDecoder, PRINCE2 7, Managementprodukte</footer>
</blockquote>

Found a mistake? Let us know, we check every report.