Estimate to complete
abbr. ETC
Definition
The estimate to complete looks only ahead. It states which costs will still arise from the cut-off date until all the work is finished. The most reliable approach is a fresh estimate of the open work packages by the people responsible for them; a quick approximation can be extrapolated from the remaining budget and the performance indices so far. Added to actual cost, it gives the estimate at completion.
Equivalents in other frameworks
Concept Expected cost of the remaining work · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Estimate to complete | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Estimate to complete
- Topic area
- Monitoring and control
Distinction
The remaining budget, that is, budget at completion minus earned value, says what the open work may cost according to plan. The estimate to complete says what it is likely to cost. If the two differ significantly, that is an early warning sign, even if the cost variance so far is still small.
In practice
When a data centre is being built, three work packages with a remaining budget of 600,000 euros are still open after eight months. Those responsible re-estimate them: the air-conditioning will cost 80,000 euros more because of higher prices, the cabling 20,000 euros less. The estimate to complete is therefore 660,000 euros. Because these additional costs have not yet been incurred, they do not appear in any cost variance, but they do show up in the forecast.
Frequently asked questions
Who prepares the estimate to complete?
Ideally the people responsible for the outstanding work, such as the control account managers. The project manager checks the estimates for plausibility.
May the estimate be lower than the remaining budget?
Yes, if the work can genuinely be done more cheaply, for example thanks to better prices. A strikingly low estimate should, however, be justified.
Source and context
- Reference
- ISO 21506:2024, 3.26
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Estimate to complete. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/estimate-to-complete/
Hain, D. (n.d.): Estimate to complete. PMDecoder, entry on ISO 21506:2024, 3.26. https://pmdecoder.com/en/glossary/estimate-to-complete/ (retrieved 24 November 2026)
@misc{estimatetocomplete,
author = {Hain, Dennis},
title = {Estimate to complete},
note = {PMDecoder, ISO 21506:2024, 3.26},
url = {https://pmdecoder.com/en/glossary/estimate-to-complete/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/estimate-to-complete/"> <p>Expected cost of all the work still outstanding at the cut-off date, for example in a project or a single work package.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/estimate-to-complete/">Estimate to complete</a>, PMDecoder, ISO 21506:2024, 3.26</footer> </blockquote>
Found a mistake? Let us know, we check every report.