Topic area

Monitoring and control

Terms for monitoring and control: plan-versus-actual comparison, earned value, forecasts, changes and actions that keep a project on course.

87 terms

Concepts in this topic area

  • Action against a potential deviationThe action that removes the cause of a possible future deviation or defect before it occurs, so that project performance stays in line with the plan.Preventive action · Preventive action
  • Action against an occurred deviationThe action that remedies a deviation that has already occurred, ideally by addressing its cause, and brings project performance back into line with the plan.Corrective action · Corrective action
  • Actual cost of work performedThe costs actually incurred for the project work performed up to a data date; in earned value analysis, the value compared with earned value.Actual cost · Actual cost
  • Approved reference version of a planThe approved version of scope, schedule or cost against which actual progress is measured; changes to it only through the change control process.Baseline · Baseline
  • Body deciding on changesThe formally designated body that reviews change requests and decides on their approval, rejection or deferral before baselines are adjusted.Change control board · Change control board · Change Authority
  • Budgeted value of planned workThe budget for the work that the baseline plans to complete by a data date; the reference value for schedule variance and schedule performance index.Planned value · Planned value
  • Controlled handling of changesThe process by which changes to the scope, schedule, cost or results of a project are requested, assessed, decided on, implemented and documented.Change control · Change control · Issues practice · Issue Management Approach
  • Cost efficiency of work performedThe ratio of earned value to actual cost; a value below one shows that more has been spent than planned for each unit of work actually performed.Cost performance index · Cost performance index
  • Cumulative development over the project durationThe curve of cumulative costs, hours or work over time, whose typical S shape makes the comparison of plan and actual over the course of the project clear.S-curve · S-curve analysis
  • Decision point between project phasesThe defined point at the end of a project phase at which agreed criteria are used to decide whether the project continues, changes course or is stopped.Gate · Phase gate · Phase Gate · Tollgate · Managing a stage boundary
  • Difference between earned value and actual costThe metric that shows whether the work performed up to a data date has cost more or less than planned; a negative value indicates a cost overrun.Cost variance · Cost variance
  • Difference between earned value and planned valueThe metric that expresses in budget terms whether a project has completed more or less work than planned by the data date; negative means behind schedule.Schedule variance · Schedule variance
  • Difference between plan and actualThe measurable difference between planned and actual value, for example in cost, schedule or performance, as a trigger for analysis and control.Variance · Variance
  • Estimate of final dates and costsThe estimate, based on the current status, of when a project is likely to end and what it will cost in total; updated with each new set of data.Project forecast · Forecast
  • Evaluating development across several data datesThe analysis of how metrics, dates or costs develop over several reporting points in order to detect changes early and to derive forecasts from them.Trend analysis · Trend analysis
  • Examining plan-versus-actual differencesThe examination of how far and why planned and actual values of cost, schedule or performance differ, as the basis for deciding on suitable actions.Variance analysis · Variance analysis
  • Expected budget variance at completionThe difference between budget at completion and estimate at completion, which shows how far the project is likely to end over or under budget.Variance at completion · Variance at completion
  • Expected cost of the remaining workThe forecast of what the work of a project or a single work package not yet completed is expected to cost from the data date through to completion.Estimate to complete · Estimate to complete
  • Expected total cost at completionThe current forecast of the total cost of a piece of work or a project, made up of actual costs and the estimate for the work still outstanding.Estimate at completion · Estimate at completion
  • Formal request to change what was agreedThe formal, documented proposal to change the scope, dates, costs or other agreed baselines of a project, which must be reviewed and decided upon.Change request · Change request
  • Management unit for scope, budget and scheduleThe point in the project structure at which scope, budget, actual cost and schedule are brought together and performance is measured using earned value.Control account · Control account
  • Managing components and versions of a resultThe task of recording the characteristics, components and versions of a result and controlling changes traceably so that it is clear which version applies.Configuration management · Configuration management system · Product Register
  • Monitoring and controlling a projectThe ongoing comparison of project status with the plan and the initiation of corrective actions when schedule, cost, scope or quality deviate from it.Control · Progress practice · Monitor & Control · Controlling a stage
  • Occurring problem that needs resolutionAn existing question or difficulty in the project that must be dealt with and decided; unlike a risk, it is not uncertain but has already occurred.Issue · Issue
  • Performance measurement using earned valueThe technique that compares planned work, work actually performed and actual cost at a data date in order to assess cost and schedule status together.Earned value management · Earned value management
  • Permitted margin for deviationsThe predefined limit up to which deviations from plan, upwards or downwards, are accepted without a decision by the level above; beyond it, that level steps in.Variance threshold · Tolerance (PRINCE2)
  • Reference date for recorded project statusThe defined point in time at which actual data is recorded and to which progress, variances and forecasts in reports and in the schedule refer.Status date · Data date
  • Register of issuesThe continually maintained list of all open issues in a project, recording their description, owner, actions, due date and current resolution status.Issue register · Issue log · Issue Register
  • Schedule efficiency of work performedThe ratio of earned value to planned value; a value below one shows that the project is performing work more slowly than the baseline provides for.Schedule performance index · Schedule performance index
  • Share of work completedThe share of the planned work of an activity, work package or project that has been completed at a data date, usually expressed as a percentage.Percent complete · Percent complete
  • Software environment for project dataThe entire set of software tools with which the plans, resources, costs, documents and reports of a project are recorded, linked and analysed.Project management information system · Project management information system
  • Time-phased baseline for performance measurementThe approved, time-phased plan of scope, schedule and budget, excluding management reserve, against which actual performance is measured in earned value.Performance measurement baseline · Performance measurement baseline
  • Total budget of the planned workThe sum of all budgets established for the work of a project, work package or control account; reference value for forecasts in earned value.Budget at completion · Budget at completion
  • Value of work performedThe value, expressed in budget terms, of the work actually completed up to a data date; the key figure for determining cost and schedule variances.Earned value · Earned value

All concepts compared