Activity

Definition

In PMI usage, an activity is a clearly delimited piece of work that is scheduled and carried out within a project. Activities are created by breaking down work packages into specific tasks. Each activity has an identifier, a description and further attributes such as duration, required resources, predecessors and successors, and early and late dates. Linked by logical relationships, activities form the schedule model from which the project schedule and the critical path are calculated.

Equivalents in other frameworks

Concept Defined piece of work with a start and finish · three frameworks reviewed

Equivalents of Activity in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Activityequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Activity
Narrower term
Successor activity
Topic area
Scheduling

Distinction

The activity as defined in ISO 21506 denotes the same thing; this entry gives the PMI view. A work package describes a part of the scope, whereas an activity is a task required to produce it. A milestone is a point in time with no duration, and a summary activity groups several activities together.

In practice

The work package “Training for customer advisers” is broken down into four activities: prepare training materials, agree dates with the branches, deliver the training and evaluate feedback. The materials take ten working days and must be finished before the training sessions. Agreeing dates can run in parallel. Each activity is given a responsible person and appears in the project schedule accordingly.

Frequently asked questions

What are the attributes of an activity?

Besides identifier and description, typically duration, predecessors and successors, type of relationship, required resources, location, responsible persons and dates. PMI refers to these as activity attributes.

How granular should activities be?

Granular enough for duration and resources to be estimated and for progress to be visible within the reporting cycle. Activities that are too fine increase maintenance effort without improving control.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Activity. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/activity-pmi/

Short form

Activity (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/activity-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{activitypmi,
  title   = {Activity},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/activity-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/activity-pmi/">
  <p>In PMI usage, a clearly delimited piece of project work that is planned in the schedule.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/activity-pmi/">Activity</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.