Lead

Definition

A lead is a time value on a logical relationship that allows a successor to start earlier than the relationship alone would permit. In a finish-to-start relationship with a lead of five days, the successor starts five days before the predecessor finishes. This makes it possible to represent overlaps when part of the predecessor is enough to begin the follow-on work. Many scheduling tools enter a lead as a negative lag.

Equivalents in other frameworks

Concept Brought-forward start relative to the predecessor · three frameworks reviewed

Equivalents of Lead in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Leadequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Lead

Distinction

Lead corresponds to the German Vorlaufzeit in ISO 21506. Its counterpart is lag, which delays the successor. Overlapping activities with leads to shorten a plan is fast tracking. A lead is not the same as a start-to-start relationship: both allow overlap, but the lead remains tied to the predecessor's finish.

In practice

When a corporate film is produced, editing can start before all shooting days are over, because the first scenes are already available. The production manager links “filming” and “editing” with finish-to-start and a lead of three days. The project gains three days but accepts that reshoots may still change the edit.

Frequently asked questions

What risk does a lead bring?

The successor starts on an incomplete basis. If the predecessor's result still changes, rework may follow. Leads should therefore only be used where the partial results are stable enough.

Can a lead be applied to other relationship types?

Yes, in principle to all four. It is most common and easiest to understand, however, with finish-to-start relationships.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Lead. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/lead-pmi/

Short form

Lead (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/lead-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{leadpmi,
  title   = {Lead},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/lead-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/lead-pmi/">
  <p>Advance on a schedule link that lets the successor begin earlier than the relationship alone would allow; often entered as a negative lag.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/lead-pmi/">Lead</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.